Hi Experts,
Good day
Can anyone pls need assistance on how can i change the Project Completed column status in new column.
If the Project Completed is 100 = Completed
if the Project Completed is greaterthan 0 but lessthan 100 = In-Progress
if the Project Completed is blank or 0 = Not started
Thank you
You can create a custom column using the SWITCH function as follows:
Status Custom Column = SWITCH( TRUE(), [Project Completed] = 100, "Completed", [Project Completed] > 0 && [Project Completed] < 100, "In-Progress", ISBLANK([Project Completed]) || [Project Completed] = 0, "Not started" )
=-=-=-=-=-
If you find this insightful, please provide a Kudo and accept this as a solution so that other members may find it easier.
3 Replies
- fooddCommunity Champion
You can create a custom column using the SWITCH function as follows:
Status Custom Column = SWITCH( TRUE(), [Project Completed] = 100, "Completed", [Project Completed] > 0 && [Project Completed] < 100, "In-Progress", ISBLANK([Project Completed]) || [Project Completed] = 0, "Not started" )
=-=-=-=-=-
If you find this insightful, please provide a Kudo and accept this as a solution so that other members may find it easier.- AllanBercesPost Prodigy
Hi foodd Thank you very much, working perfectly
- fooddCommunity Champion
Your welcome.