Filter active projects based on selected date range
Hey all,
I am working with data that looks very much like the following -
| Team | Project | Start | Finish |
| Team A | 1 | 10/10/2021 | 3/2/2022 |
| Team A | 2 | 1/1/2022 | 2/1/2022 |
| Team B | 3 | 8/4/2021 | 5/1/2022 |
| Team B | 4 | 2/2/2022 | 2/20/2022 |
| Team B | 5 | 1/5/2022 | 4/10/2022 |
| Team C | 6 | 3/8/2022 | 4/10/2022 |
My goal is to filter all active Projects in a Gantt/Table for specific Months or custom Date Range, as well as selected Team.
Based on many recommendations on the forum, I have tried creating a Date dimension table and using min/max to filter projects out, but I am not sure how to create a relationship with the main table so that I can filter Team. If I connect Date > Finish, then the Month filter only works for projects ending on that specific month, and I cannot have multiple relationships for Start. Was trying to use USERELATIONSHIP but was unable to make it work.
Another possible solution that came to mind is to have a calculated column that has a filtering value based on the selected date value, but not sure how to make it work for a range.
I will also use the result to get a weighted average based on how long the project was active per month per team.
Any advice is appreciated!!
Sorry I had my filters the wrong way round see if it's any better now? (Same link)
Project Filter = VAR EarliestVisibleDate = MIN ( 'Date'[Date] ) VAR LatestVisibleDate = MAX ( 'Date'[Date] ) VAR FilteredProjects = FILTER ( Project, Project[Finish] >= EarliestVisibleDate && Project[Start] <= LatestVisibleDate ) RETURN INT ( NOT ( ISEMPTY ( FilteredProjects ) ) )
Alternatively have a look at the second file on the same link. It uses power query to transform your table into a row per day per project:This has the advantage of just being able to use a straight relationship.
Hope it gives you some ideas!
5 Replies
- bcdobbsCommunity Champion
So you have two main options.
First one is to leave your date table disconnected and do all the work in DAX.Add a measure like:
Project Filter = VAR EarliestVisibleDate = MIN ( 'Date'[Date] ) VAR LatestVisibleDate = MAX ( 'Date'[Date] ) VAR FilteredProjects = FILTER ( Project, Project[Start] >= EarliestVisibleDate && Project[Finish] <= LatestVisibleDate ) RETURN INT ( NOT ( ISEMPTY ( FilteredProjects ) ) )And use it as a visual filter set to 1:
My prefered option is to change the grain of your table so there is one row per day. I'll send an example shortly.
- AnonymousNot applicable
The first option doesn't seem to work. I believe it does not apply to tasks that have their start/finish outside of the date range, which are also active projects.
- bcdobbsCommunity Champion
Sorry I had my filters the wrong way round see if it's any better now? (Same link)
Project Filter = VAR EarliestVisibleDate = MIN ( 'Date'[Date] ) VAR LatestVisibleDate = MAX ( 'Date'[Date] ) VAR FilteredProjects = FILTER ( Project, Project[Finish] >= EarliestVisibleDate && Project[Start] <= LatestVisibleDate ) RETURN INT ( NOT ( ISEMPTY ( FilteredProjects ) ) )
Alternatively have a look at the second file on the same link. It uses power query to transform your table into a row per day per project:This has the advantage of just being able to use a straight relationship.
Hope it gives you some ideas!