Forum Discussion
Anonymous
6 years agoNot applicable
Gantt chart with reference vertical lines
Expected chart: y-axis: Tasks x-axis: Dates Reference lines(more than one): some specific dates For plotting I'm using custom visual - Gantt (version-2.2.3.0) from power bi market pl...
Anonymous
6 years agoNot applicable
Hello, v-evelk Thanks for your response.
But my milestones(ref's lines) are dependent on Project name and not on Tasks. Those are random dates which I have to plot on the visual. Which will come up as a straight line as shown in my post above.
v-evelk
6 years agoMicrosoft Employee
You are right that milestone records are considered as tasks but task records are just containers for them in this case.
In fact, you can call your milestone records as "ProjectName Milestone [1|2|3]" to show relation with a certain project.
Kind Regards,
Evgenii Elkin,
Software Engineer
Microsoft Power BI Custom Visuals