Integrated Master Schedule to Powerbi
Hi, I have an integrated master schedule that I have stored on a SharePoint site. It is an MPP file. How do I connect this master schedule to powerbi? I have heard to use Odata and I tried connecting as a sharepoint folder but I get errors. I am not sure what route is correct.
Thank You,
Marlene
Solved! Go to Solution.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content

Hi Marlene,
You can't connect to MPP files from Power BI (without an expensive connector). You'll need to get a Project Online licence and connect to the online version.
Pete
Now accepting Kudos! If my post helped you, why not give it a thumbs-up?
Proud to be a Datanaut!

- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content

Thanks Pete. I'll have to export to excel for now because I cannot get admin access to pull the odata from the pwa site. work policies
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content

Hi Marlene,
You can't connect to MPP files from Power BI (without an expensive connector). You'll need to get a Project Online licence and connect to the online version.
Pete
Now accepting Kudos! If my post helped you, why not give it a thumbs-up?
Proud to be a Datanaut!

Helpful resources
Join our Fabric User Panel
This is your chance to engage directly with the engineering team behind Fabric and Power BI. Share your experiences and shape the future.
Power BI Monthly Update - June 2025
Check out the June 2025 Power BI update to learn about new features.

User | Count |
---|---|
9 | |
6 | |
6 | |
5 | |
5 |
User | Count |
---|---|
11 | |
11 | |
9 | |
6 | |
6 |