Anonymous
Not applicable
Partially syndicated - Outbound

Integrated Master Schedule to Powerbi

Hi, I have an integrated master schedule that I have stored on a SharePoint site. It is an MPP file. How do I connect this master schedule to powerbi?  I have heard to use Odata and I tried connecting as a sharepoint folder but I get errors. I am not sure what route is correct. 

 

Thank You, 

Marlene 

1 ACCEPTED SOLUTION
BA_Pete
Super User
Super User

Syndicated - Outbound

Hi Marlene,

 

You can't connect to MPP files from Power BI (without an expensive connector). You'll need to get a Project Online licence and connect to the online version.

 

Pete



Now accepting Kudos! If my post helped you, why not give it a thumbs-up?

Proud to be a Datanaut!




View solution in original post

2 REPLIES 2
avatar user
Anonymous
Not applicable

Syndicated - Outbound

Thanks Pete.  I'll have to export to excel for now because I cannot get admin access to pull the odata from the pwa site.  work policies 

BA_Pete
Super User
Super User

Syndicated - Outbound

Hi Marlene,

 

You can't connect to MPP files from Power BI (without an expensive connector). You'll need to get a Project Online licence and connect to the online version.

 

Pete



Now accepting Kudos! If my post helped you, why not give it a thumbs-up?

Proud to be a Datanaut!




avatar user

Helpful resources

Announcements
July 2025 community update carousel

Fabric Community Update - July 2025

Find out what's new and trending in the Fabric community.

July PBI25 Carousel

Power BI Monthly Update - July 2025

Check out the July 2025 Power BI update to learn about new features.

Top Solution Authors (Last Month)
Top Kudoed Authors (Last Month)