Trying to calculate Days between 2 date columns. Both Columns have nulls or no values

There is Actual Start and Actual End Date. Both columns have null values as project is in progress or no given date. Keep getting errors on below. Any suggestions? Just trying to get a number value on the difference between these 2 columns. Thanks

 

Days Between = If('BI Projects'[Actual Start]=BLANK(),"",DATEDIFF('BI Projects'[Actual Start], 'BI Projects'[Actual End],DAY))

1 ACCEPTED SOLUTION
tamerj1
Super User
Super User

Hi @ResearchDev 
PLease try

Days Between =
IF (
    'BI Projects'[Actual Start] <> BLANK ()
        && 'BI Projects'[Actual End] <> BLANK (),
    DATEDIFF ( 'BI Projects'[Actual Start], 'BI Projects'[Actual End], DAY )
)

View solution in original post

3 REPLIES 3
ResearchDev
Helper II
Helper II

Thanks so much! Worked like magic!

tamerj1
Super User
Super User

Hi @ResearchDev 
PLease try

Days Between =
IF (
    'BI Projects'[Actual Start] <> BLANK ()
        && 'BI Projects'[Actual End] <> BLANK (),
    DATEDIFF ( 'BI Projects'[Actual Start], 'BI Projects'[Actual End], DAY )
)

Thanks so much!

Helpful resources

Announcements
Las Vegas 2025

Join us at the Microsoft Fabric Community Conference

March 31 - April 2, 2025, in Las Vegas, Nevada. Use code MSCUST for a $150 discount!

FebPBI_Carousel

Power BI Monthly Update - February 2025

Check out the February 2025 Power BI update to learn about new features.

Feb2025 NL Carousel

Fabric Community Update - February 2025

Find out what's new and trending in the Fabric community.

Top Kudoed Authors