Hi All,

 

I've been using PowerBI for the better part of a year now. For the last month and a half or a little more, we've had annoying failures to refresh for 6 of our 14 tile visualizations. It's also inconsistent. Some days certain tiles of the 6 refresh and others they don't. The dashboard in question contains nothing more than 14 pinned single data point cards. They are simple queries made to our Azure SQL Database. On the database, all the queries run immediately with no delay. I have all my visualizations set to connect live to our Azure database. I'm at a loss for what to do. It seems like it's an issue with resources on Microsoft's servers. Here's the error I get:

 

Resources Exceeded
 
This visual has exceeded the available resources. Try filtering to decrease the amount of data displayed.
Please try again later or contact support. If you contact support, please provide these details.

 

Activity IDc7b563f3-c93d-2aa1-2784-082b8d81f234
Request IDe4c3c75a-060f-6b40-8ab0-7ed194ba10c3
Correlation ID69832fcb-c121-4ed4-ca06-89d5275e48e2
TimeThu Jan 19 2017 11:09:24 GMT-0500 (EST)
Version13.0.1700.1003

 

1 ACCEPTED SOLUTION
v-ljerr-msft
Employee
Employee

Hi @jgarciabu,

 

Yes, the issue occurs when a visual has attempted to query too much data for the server to complete the result with the available resources.

 

As suggested in the error, you may need to try filtering the visual to reduce the amount of data in the result currently.Smiley Happy

 

Regards

View solution in original post

41 REPLIES 41
DhananjayWalunj
New Member

Hi All,

 

Is there an option to show the icon on the page and it will be visible only when the report shows the error "visual has exceeded available resources" and after clicking that icon we will jump to the default view where the icon is invisible?

akkitek
Helper III
Helper III

I'm having the same error for one of the table visuals but the same visual works fine when I publish it to "My workspace". Is there a difference in how personal workspace capacity and Azure capacities are configured? 

pwrbiadm
Helper I
Helper I

Can someone please provide the soultion to the issue "exceeded the available resources"?

 

I am unable to understand what is wrong? I don't have large DAX calculations. I have only added 4-6 more columns in one or two tables. My other visuals on the tabs on desktop has larger queries and measures. They all are running and refreshing just fine. I am having issue with just one visual. It doesn't make sense why with just one visual? 

Anonymous
Not applicable

I was able to get around this issue by identifying which table caused the slow down. I turned off "Enable load" for that table.  Then referenced the result of that table into a new table which I loaded into the report.  By keeping the most complex calculations in the background query and only loading its results, my report went from taking 20 minutes to return an error to returning accurate results within 5 seconds. 

Anonymous
Not applicable

Hi,

Any  updates on this topic yet?

I'm having the strange thing that when I use publish to the web for my report I get the screenshot below as a result.
Only 1 out of 2 visuals is showing and the other one gives the exceeded memory error. Strangely both visuals (a table and a graph) use exactly the same data and filters (page level filters).

I had 2 years of logfiles and already filtered out 1 year with a report level filter but still keep having this issue.
The biggest DAX that I have is my own calendar table. Furthermore I have quite some Power Query steps.

Any suggestions on what to do?

screenshot report.png

@Anonymous 

I managed to get around my issue without really intending to. I was looking to improve the performance of my report and rewrote all of my DAX measures using variables. Even a measure as simple as just summing some column was written using a variable and returning the output. The performance of the dashboard was drastically improved and it resolved my issue with the exceeded memory error. SQLBI has a Date table publicly available that you can borrow if you have trouble rewriting your DAX for the table. It's actually a great date table. It has pretty much everything you could possibly want in a date table. Hope this helps!

hi @bdmichael09 , can you provide a DAX example?

 

Thanks.

@cittakaro Sure. None of my DAX is too crazy and is probably pretty basic to someone who is an expert. There might be better ways to do most of what I did but it works and loads quickly so I got what I needed. 

 

This is probably one of the more complicated measures I had in my report. I used to have everything here that you see as variables written into what is now the return statement. Sorry if it seems a bit like a jumbled mess. It's essentially just a series of nested if statements. After I started using variables, the performance of the report loading visuals was almost instantaneous rather than taking upwards of 10-15 seconds just to load a matrix/table visualization, if it loaded those visuals at all. 

 

EarnedTitleLevel# = 
VAR SurveylessthanTitle = [SurveyScoreGoal]<=values(TMD[Title Sort])
var SClessthanTitle = [StatusCountGoal]<=values(TMD[Title Sort])
var TTlessthanTitle = [TurnTimeGoal]<=values(TMD[Title Sort])
var AnswerlessthanTitle = [AnswerRateGoal]<=values(TMD[Title Sort])
VAR SurveylessthanSC = [SurveyScoreGoal]<=[StatusCountGoal]
var SClessthanSurvey = [StatusCountGoal]<=[SurveyScoreGoal]
VAR SurveylessthanTT = [SurveyScoreGoal]<=[TurnTimeGoal]
var TTlessthanSurvey = [TurnTimeGoal]<=[SurveyScoreGoal]
var SurveylessthanAnswer = [SurveyScoreGoal]<=[AnswerRateGoal]
var AnswerlessthanSurvey = [AnswerRateGoal]<=[SurveyScoreGoal]
var TTGoal = [TurnTimeGoal]
var SurveyScore = [SurveyScoreGoal]
var MinSurveys = [SurveyReceivedMin]
var MinCR = [CRCountMin]
var AnswerGoal = [AnswerRateGoal]
var statusgoal = [StatusCountGoal]
var CurrentTitle = values(TMD[Title Sort])
return

if(values(TMD[Specialty])="Mainstream PS" || values(TMD[Specialty])="NY PS",
    if(isblank(TTGoal) || isblank(SurveyScore), CurrentTitle,
    if(MinCR = -1 || MinSurveys = -1,
        if(SurveylessthanTitle && SurveylessthanTT,SurveyScore,
        if(TTlessthanTitle && TTlessthanSurvey,TTGoal,CurrentTitle)),
    if(SurveylessthanTT,SurveyScore,TTGoal))),
if(values(TMD[Specialty])="Hunt PS",
    if(isblank(statusgoal) || isblank(SurveyScore), CurrentTitle,
    if(MinSurveys = -1 || [RONAgoal]=-1,
        if(SurveylessthanTitle && SurveylessthanSC,SurveyScore,
        if(SClessthanTitle && SClessthanSurvey,statusgoal,CurrentTitle)),
    if(SurveylessthanSC,SurveyScore,statusgoal))),
if(values(TMD[Specialty])="CCS" || values(TMD[Specialty])="Escalation CCS",
    if(isblank(statusgoal) || isblank(SurveyScore), CurrentTitle,
    if(MinSurveys = -1,
        if(SurveylessthanTitle && SurveylessthanSC,SurveyScore,
        if(SClessthanTitle && SClessthanSurvey,statusgoal,CurrentTitle)),
    if(SurveylessthanSC,SurveyScore,statusgoal))),
if(isblank(AnswerGoal) || isblank(SurveyScore), CurrentTitle,
    if(MinSurveys = -1,
        if(SurveylessthanTitle && SurveylessthanAnswer,SurveyScore,
        if(AnswerlessthanTitle && AnswerlessthanSurvey,AnswerGoal,CurrentTitle)),
    if(SurveylessthanAnswer,SurveyScore,AnswerGoal))))))

 

A slightly simpler example is below here. Just for a bit of context that would make the code make a bit of sense without seeing the report, on each page of this report I've added in drop down slicers that the end user can use as selectors to adjust their goals for different tiers. Each of those slicers is reading off of a simple table that just has values that range from 0-100.

TurnTimeGoal = 
var CRCount = [CR Count]
var TT = [TurnTime]
var TCGoal = selectedvalue(TurnTimeTC[Column1])
var PCGoal = selectedvalue(TurnTimePC[Column1])
var ExecGoal = selectedvalue(TurnTimeExec[Column1])
var SrGoal = selectedvalue(TurnTimeSenior[Column1])
return

if(isblank(CRCount),blank(),
if(values(TMD[Specialty])="Mainstream PS" || values(TMD[Specialty])="NY PS",
    if(TT<TCGoal,4,
    if(TT<PCGoal,3,
    if(TT<ExecGoal,2,
    if(TT<SrGoal,1,0)))),blank()))

 

Anonymous
Not applicable

Follow up:

 

Is there any update, I am sitting at client's heat and don't have any words at the visual exceed limit error at power BI service reports.

 

Can anybody help me with this?

Dear all

 

We were dealing with this issue a year and a half ago and it was an absolute pain. We had numerous conversations with the official Microsoft support at the time and, in all honesty, they couldnt help much except for advising us that the issue was our SQL Server (queriestaking more than 5 seconds...); limit the number of the visuals in a single report. In a nutshell, limit the amount of data to be fetched; make sure to put solid indexing. 

 

So:

 

1. Check the SQL query performance. End-result in Power BI depends on the performance of your backend. 

2. Further tune it with indexing. 

3. Consider having an SSAS solution of your data instead of taping on schema tables directly.

 

good luck. 

 

 

Anonymous
Not applicable

I am having the same issue!!

 

"visual has exceeded the available resources"Untitled.png

 

Can anybody help me out, I am at the on-site project and prepared 100+ reports.

Report having an issue of visual limit and no data is able to show but the report is not that much big only few measures are calculating.

 

Please, can anybody help me out?

 

bdmichael09
Helper II
Helper II

I just ran into this problem today. I modified a report that I had previously published. The original report worked completely fine. The longest load time was maybe 5 seconds. In this 2nd itteration of the report, I modified one of the measures to use some more complicated logic. I also removed some measures from the model. The data set (which is a set of excel files) is literally the exact same. I've not added anything. At first it worked just fine. I came back to it today and made 0 changes but somehow now it is saying Visual has exceeded available resources. It makes no sense. 

juresti
Frequent Visitor

I also had this issue today.

This is what I found. I had a data set with 5 years of data and a visual displaying the last 5 days of data by default.

As soon as I went to 6 days the resources are exceeded.

 

I modified my desktop PBI to 2 years then I could go past viewing over the last 6 days of data.

 

Most likely the available resoruces are (data set size + visual memory usage + calculations / queries memory usage)

 

Of course the moderators will only repeat the documentation as the solution since they are not the software developers.

"The documentation is the final answer and correct"

 

Follow up:

 

I updated my date ranges once again to reproduce the error to confirm and the resources are not exceeded anymore.

 

My test outcome was not valid. So this must be an issue within the servers since my original dataset did not reproduce the error.

 

Anonymous
Not applicable

It must be so, that you have a random number of capacity as a Pro user, and then sometimes your organization is lower the threshhold and sometimes over. Then you get errors. Go figure.

Anonymous
Not applicable

Hi

 

I have the same problem. It says in the details "The query exceeded the maximum memory allowed for queries executed in the current workload group."

 

So it refers to the Power BI service. Works fine on desktop, not when I publish this to organization.

 

denR
Advocate I
Advocate I

There are several topics where this issue is mentioned, but it looks like this one has the extensive discussion. I'd like to know what resources we're talking about. Is it CPU or memory? Is the limit on the server hosting SSAS, on the Gateway server, on the pc/laptop running Power BI Desktop/Service or is the limit on Microsofts side so that we cannot upgrade the resources that are being exceeded? If anyone knows anything about this, I would really appreciate it if you'd share it here.

ballade4
Frequent Visitor

Also having this issue. Does not make sense. Need to understand limits better as it is turning a supposedly enterprise-level tool into a bear for certain critical tasks within my relatively-small dataset.

I am having the same issues. The dataset is not huge but I do have a number of measures becasue I need the model to be dynamic. The model works on the desktop (slow but works), but in the serivce it sometimes works and sometimes crashes. Also, I have noticed that the "spinning wheel" that used to tell me if the system was still calculating, is now gone and so I have no idea when all the calculations are compleded (I assume it vanishes when a model is nearing the resource limit). It's quite frustrating becasue you start to think that the model is stuck and then all of a sudden the data in refreshes. 

 

Is this all becasue we are not signed up to Premium Capacity? Other than major corporations, who can afford Premium Capacity at $4,000/month (or more)??? And then you start looking at Microsoft's pricing model for usage you start to wonder how anyone can really understand what their monthly bill is ever going to be. I call it the "Rube Goldberg Pricing Model". Very frustrating.

Hello,

 

Would someone confirm if this is a Premium / Pro issue? Either I change my DAX or I don't know what to do. It seems that every time I upload my data I am going to see this issue. 

I just hope Microsoft bring us a solution.

 

Cheers

Helpful resources

Announcements
Fabric Community Conference

Microsoft Fabric Community Conference

Join us at our first-ever Microsoft Fabric Community Conference, March 26-28, 2024 in Las Vegas with 100+ sessions by community experts and Microsoft engineering.

February 2024 Update Carousel

Power BI Monthly Update - February 2024

Check out the February 2024 Power BI update to learn about new features.

Fabric Career Hub

Microsoft Fabric Career Hub

Explore career paths and learn resources in Fabric.

Fabric Partner Community

Microsoft Fabric Partner Community

Engage with the Fabric engineering team, hear of product updates, business opportunities, and resources in the Fabric Partner Community.

Top Solution Authors
Top Kudoed Authors