Hello,
I have integrated my Project for the Web portfolio into powerbi and am now creating visuals to represent my data. When using the GANTT chart visual, I am having trouble getting it to display summary tasks and their child tasks. Currently it displays all summary tasks and their children in the same list. I do not see a DATA category that will help with this either.
Hi, @nolafram
Ensure you have the Gantt chart visual imported into Power BI.
Make sure your data includes columns for Task Name, Start Date, End Date, Duration, and Parent Task. The Parent Task column is crucial for organizing tasks hierarchically. I create sample data, and put them in Gantt visual:
You can learn more from the following links:
Visual Awesomeness Unlocked – Gantt chart | Microsoft Power BI Blog | Microsoft Power BI
How to Customize Gantt Chart in Power BI - Zebra BI
How to Get Your Question Answered Quickly
Best Regards
Yongkang Hua
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.
Thank you for your reply, I am able to get all that data to show in my GANTT chart. What I am referring to is projects like this in project for the web:
Power BI does not recognize the multiple summary tasks and instead populates them all together as individual tasks like this:
I am trying to get Power BI to recognize the summary tasks