Hi,

I suddenly started getting "Resources Exceeded" for my main KPI table. Yestarday everything was just fine, and today it can't even load.

 

When I check performance analyser I get crazy numbers:

tslowik131_0-1638811117589.png

However, when I go to the dax studio everything seems "fine" (This is a switch table with 11 branched measures, so it normally takes a couple of seconds to load)

tslowik131_1-1638811479754.png

Individual measures all take less than 100ms to load and have around 20SE Queries.


Does anyone have a suggestion what may be a root cause here?

1 ACCEPTED SOLUTION
tslowik131
Frequent Visitor

We found a solution - we had to upgrade the capacity to gen 2 and now everything works

View solution in original post

2 REPLIES 2
ssze
Helper II
Helper II

hi @tslowik131 

what do you mean by upgrade capacity to Gen 2? i'm running into the same issue so just wondering how i can deal with it. 

Cheers!

tslowik131
Frequent Visitor

We found a solution - we had to upgrade the capacity to gen 2 and now everything works

Helpful resources

Announcements
Power BI DataViz World Championships

Power BI Dataviz World Championships

The Power BI Data Visualization World Championships is back! Get ahead of the game and start preparing now!

December 2025 Power BI Update Carousel

Power BI Monthly Update - December 2025

Check out the December 2025 Power BI Holiday Recap!

FabCon Atlanta 2026 carousel

FabCon Atlanta 2026

Join us at FabCon Atlanta, March 16-20, for the ultimate Fabric, Power BI, AI and SQL community-led event. Save $200 with code FABCOMM.