Does anyone know if its possible to merge 2 x P3 capacities (to create a P4) easily?
Or is it a case of removing a capacity, then increasing the size of the existing one to P4 size? I guess that could cause some disruption though.
Solved! Go to Solution.
hey @calamityjen ,
Depending on your need, you can increase the capacity of an existing premium capacity - that would give you the "merge" level of capacity. There is no "merge" capability of taking two separate capacities and putting them together.
So, if you ramp up one of your capacities, you will have to go through and reset all of your workspaces to the one ramped up capacity. This inclused reworking all of your gateway usage. Which, if you are modifying the gateway, you will have to have every report that uses that gateway to be re-worked to point to the gateway on the ramped up capacity.
And, unfortunately, there is no "gateway transfer" or "capacity transfer" capability to do this in one shot.
Proud to be a Datanaut!
Private message me for consulting or training needs.
hey @calamityjen ,
Depending on your need, you can increase the capacity of an existing premium capacity - that would give you the "merge" level of capacity. There is no "merge" capability of taking two separate capacities and putting them together.
So, if you ramp up one of your capacities, you will have to go through and reset all of your workspaces to the one ramped up capacity. This inclused reworking all of your gateway usage. Which, if you are modifying the gateway, you will have to have every report that uses that gateway to be re-worked to point to the gateway on the ramped up capacity.
And, unfortunately, there is no "gateway transfer" or "capacity transfer" capability to do this in one shot.
Proud to be a Datanaut!
Private message me for consulting or training needs.
Hi @collinq - I suspected it'd be a case of increasing one and moving everything over.. but I'd not considered gateways, sounds like a real pain. Thanks for this! Really helpful 😀
March 31 - April 2, 2025, in Las Vegas, Nevada. Use code MSCUST for a $150 discount! Prices go up Feb. 11th.
Check out the January 2025 Power BI update to learn about new features in Reporting, Modeling, and Data Connectivity.
User | Count |
---|---|
29 | |
28 | |
22 | |
22 | |
19 |
User | Count |
---|---|
53 | |
36 | |
28 | |
24 | |
21 |