11 years agoI can't get schedule refresh working. What am I doing wrong?!
Schedule Refresh is greyed out for my dataset (Azure SQL database) in PowerBI. It says: "You cannot schedule refresh for this dataset because it gets data from sources that currently don't suppo...
majort
11 years agoNew Member
i have the same problem. i found the affected table in my dataset but this table has no date/datetime column. So when i remove this table then schedule refresh works.
i am still investigating the problem.
majort
11 years agoNew Member
I found an issue with nvarchar columns. Converting the columns to varchar worked for me. Really strange, .. :-/ Not sure if there will be some other issues.