Create Azure Devops BurnDown chart in PowerBI
- 5 years ago
Hi Anonymous
Each query contains the following strings that you must substitute with your values. Don't include brackets {} with your substitution. For example if your organization name is "Fabrikam", replace {organization} with Fabrikam, not {Fabrikam}.
- {organization} - Your organization name
- {project} - Your team project name, or omit "/{project}" entirely, for a cross-project query
- {areapath} - Your Area Path. Example format: Project\Level1\Level2
If you still have some question, please don't hesitate to let me known.
Best Regards,
Link
Is that the answer you're looking for? If this post helps, then please consider Accept it as the solution. Really appreciate!
Hi Anonymous
Is your issue solved?
If the issue has been solved, please adopt the solution to help others.
If you still have some question, please don't hesitate to let me known.
Best Regards,
Link
Is that the answer you're looking for? If this post helps, then please consider Accept it as the solution. Really appreciate!
Hi Link,
Yes, i have done all that, i am using with query but replaced all the value accordingly but i am unable to create a burndown report in PowerBI with the query (after replaing variables with my or details).
wanted to check and see if anyone has created the Burndown report in PowerBI sucessfully.