Hi All,

 

May I have your suggestion in setting refresh schedule for a series of linked Dataflows?

It's clearly that the Dataflows close to upstream gotta be refreshed first before the linked downstream one. Currently the Schedule time is every 1/2 hour, are you using that standard slot or are you using a different way?

 

Thanks,

Rich

1 ACCEPTED SOLUTION
Tutu_in_YYC
Super User
Super User

Hey Rich, 

Are the dataflows in the same workspace or different? If the same, it triggers refreshes for all dependant entities. If not, then you need to set a schedule.
https://docs.microsoft.com/en-us/power-query/dataflows/linked-entities#refresh-logic-in-power-bi

For scheduled, I try to leave as much buffer (typically 1hr) between downstream and upstream, because even though if a refresh is scheduled at 8.30am, it might run later than that due to various reasons such as resource queing (less of an issue if you have Premium Gen2). And of course I also consider the refresh duration of the upstream one. I am also open to other suggestions if the community has any.  

Another option is to use Power BI rest API in azure automation runbook to trigger refresh after the other refresh is done. This requires more work to set up.

View solution in original post

2 REPLIES 2
rdnguyen
Helper V
Helper V

Thanks Tutu

 

Your suggestion is helpful.

Tutu_in_YYC
Super User
Super User

Hey Rich, 

Are the dataflows in the same workspace or different? If the same, it triggers refreshes for all dependant entities. If not, then you need to set a schedule.
https://docs.microsoft.com/en-us/power-query/dataflows/linked-entities#refresh-logic-in-power-bi

For scheduled, I try to leave as much buffer (typically 1hr) between downstream and upstream, because even though if a refresh is scheduled at 8.30am, it might run later than that due to various reasons such as resource queing (less of an issue if you have Premium Gen2). And of course I also consider the refresh duration of the upstream one. I am also open to other suggestions if the community has any.  

Another option is to use Power BI rest API in azure automation runbook to trigger refresh after the other refresh is done. This requires more work to set up.

Helpful resources

Announcements
Power BI DataViz World Championships

Power BI Dataviz World Championships

The Power BI Data Visualization World Championships is back! Get ahead of the game and start preparing now!

December 2025 Power BI Update Carousel

Power BI Monthly Update - December 2025

Check out the December 2025 Power BI Holiday Recap!

FabCon Atlanta 2026 carousel

FabCon Atlanta 2026

Join us at FabCon Atlanta, March 16-20, for the ultimate Fabric, Power BI, AI and SQL community-led event. Save $200 with code FABCOMM.