Cannot get Enterprise Gateway to show after publishing Power BI report

See the attached.  This is my problem.  My datasources are an internal enterprise data warehouse running on SQL Server and a SharePoint site used to house Excel files that do not live in EDW.Power BI Gateway.png

 

 

1 ACCEPTED SOLUTION
ttinsley
Resolver I
Resolver I

I found the answer.


If I pull in just the EDW tables from SQL Server, I am able to schedule refresh.

 

If I pull in just the SharePoint tables from SQL Server, I am able to schedule refresh.

 

When I MERGE tables coming from SQL Server with those coming from SharePoint, I am NOT permitted to use data gateway or schedule a refresh.  

 

When creating a solution in a way that does not require merging of these two tables, I am in good shape.

 

ProbSteps.png

View solution in original post

1 REPLY 1
ttinsley
Resolver I
Resolver I

I found the answer.


If I pull in just the EDW tables from SQL Server, I am able to schedule refresh.

 

If I pull in just the SharePoint tables from SQL Server, I am able to schedule refresh.

 

When I MERGE tables coming from SQL Server with those coming from SharePoint, I am NOT permitted to use data gateway or schedule a refresh.  

 

When creating a solution in a way that does not require merging of these two tables, I am in good shape.

 

ProbSteps.png

Helpful resources

Announcements
November Carousel

Fabric Community Update - November 2024

Find out what's new and trending in the Fabric Community.

Live Sessions with Fabric DB

Be one of the first to start using Fabric Databases

Starting December 3, join live sessions with database experts and the Fabric product team to learn just how easy it is to get started.

Las Vegas 2025

Join us at the Microsoft Fabric Community Conference

March 31 - April 2, 2025, in Las Vegas, Nevada. Use code MSCUST for a $150 discount! Early Bird pricing ends December 9th.

Nov PBI Update Carousel

Power BI Monthly Update - November 2024

Check out the November 2024 Power BI update to learn about new features.