Hi RyanW,
At first, please note that we can only create measure and calculated column in Power Bi desktop. So I test in Power BI desktop.
After several days' test, I tried many solutions. Finally, I get the previous day's value. Please create a measure using the formula.Prvious-day-value = Var DD=MasterData[Last Run Date] RETURN CALCULATE(MAX(MasterData[CostPerTon]),FILTER(ALLSELECTED(MasterData),MasterData[ProcessDate]=DD))
Then create a measure to get the increase/decrease percentage.Percentage = (MAX(MasterData[CostPerTon])-MasterData[Prvious-day-value])/MAX(MasterData[CostPerTon])
Please download the attachments to review more details.
Best Regards,
Angelia
Hi RyanW,
>>When I use Column=IF(MasterData[ProcessDate]=MasterData[Last Run Date],MasterData[CostPerTon],0)
The entire column is populated with 0
Why the entire column is 0, you calculated [Last Run Date] by calculated column, there it it ture when MasterData[ProcessDate]=MasterData[Last Run Date]? Do you mind share your .pbix file for further analysis?
Best Regards,
Angelia
Hi Angelia,
Please see the file in the link below for more information, I have stripped out all the rest of the information and just put in some sample data but it should be enough. thanks for all your help so far.