Regular Visitor

Power BI On prime servers - upgrade to September 2025

Hello, Recently we have upgraded CCT PBI servers to 2025 September version , all existing report working fine. But ran into issues:

 

1. when promoting report with small changes from Dev to SIT , new changes are not showing up in the SIt environment .

2. Same report when I promote from Dev to UAT environment , report in UAT showing incorrect datasource information its not matching with Dev datasource.  Does anyone ran into this issue before.  Since we have upgrade all environments this has became urgent issue to resolve. Appriciate your help.

thanks

1 ACCEPTED SOLUTION

It started working after downloading report to upgraded power bi desktop and refreshed datasoruces and exported back to the server then migrated report to SIT environment. 

View solution in original post

6 REPLIES 6
v-pgoloju
Community Support
Community Support

Hi @RPBI1,

 

Great to hear that it’s working as expected on your end!
I’d suggest marking the specific reply that helped resolve the issue as the accepted solution, as this can benefit others facing similar problems. It will make it easier for community members to quickly identify and apply the right fix.

 

Thnaks & Regards,

Prasanna Kumar

v-pgoloju
Community Support
Community Support

Hi @RPBI1,

 

Just following up to see if the Response provided by community members were helpful in addressing the issue. if the issue still persists Feel free to reach out if you need any further clarification or assistance.

 

Best regards,
Prasanna Kumar

 

It started working after downloading report to upgraded power bi desktop and refreshed datasoruces and exported back to the server then migrated report to SIT environment. 

v-pgoloju
Community Support
Community Support

Hi @RPBI1,

 

Thank you for reaching out to the Microsoft Fabric Forum Community, and special thanks to @123abc  for prompt and helpful response.

 

When moving a report from Dev to SIT, Power BI sometimes keeps using the old dataset instead of fully replacing it, so new changes don’t show up unless the dataset is redeployed or removed and deployed again. When promoting to UAT, the dataset can also end up connecting to the wrong datasource or gateway without any clear warning, especially if gateways have similar names or use OAuth/user-based connections. A practical fix is to always deploy the dataset (semantic model) along with the report, re save or reapply the deployment rules, and then manually check and rebind the datasource and gateway in the target workspace.

 

Thanks & Regards,

Prasanna Kumar

123abc
Community Champion
Community Champion

Hi @123abc  : I don't see the solution to my problem with the report promotion. Can you past direct link.

 

thanks

Helpful resources

Announcements
Power BI DataViz World Championships

Power BI Dataviz World Championships

Vote for your favorite vizzies from the Power BI World Championship submissions!

Sticker Challenge 2026 Carousel

Join our Community Sticker Challenge 2026

If you love stickers, then you will definitely want to check out our Community Sticker Challenge!

January Power BI Update Carousel

Power BI Monthly Update - January 2026

Check out the January 2026 Power BI update to learn about new features.

FabCon Atlanta 2026 carousel

FabCon Atlanta 2026

Join us at FabCon Atlanta, March 16-20, for the ultimate Fabric, Power BI, AI and SQL community-led event. Save $200 with code FABCOMM.