Hi Everyone,   Colud you help with a tranformation in power query?  I need to add a new column which returns the prevous working date from list of dates.  Please see the below what I need.   Than...
  • ImkeF's avatar
    3 years ago

    Hello Monika31 ,
    I have re-created the equivalent to the Excel WORKDAY function for this exact purpose a while ago: Excel WORKDAY equivalent in Power Query and Power BI – (thebiccountant.com)

    let func =   
     (StartDate as date, Days as number, optional Holidays as list) =>                                                                    
    let
    /* Debug parameters
        StartDate = #date(2008, 10, 1),
        Days = 151,
        //Holidays = {#date(2008,11,26), #date(2008,12,4), #date(2009,1,21)},                                                                     
    */
        Holidays_ = if Holidays = null then 0 else List.Count(Holidays),
        // Create a list of days that span the max possible period                                                          
        ListOfDates =
            if Days >= 0 then
                List.Dates(
                    StartDate,
                    Number.RoundUp((Days + Holidays_) * (7 / 5) + 2, 0),
                    #duration(1, 0, 0, 0)
                )
            else
                let
                    EarliestStartDate = Date.From(
                        Number.From(
                            Date.AddDays(StartDate, Number.RoundUp((Days - Holidays_) * (7 / 5) - 2, 0))
                        )
                    ),
                    Result = List.Dates(
                        EarliestStartDate,
                        Number.From(StartDate - EarliestStartDate),
                        #duration(1, 0, 0, 0)
                    )
                in
                    Result,
        // if the optional Holidays parameter is used: Keep only those dates in the list that don't occur in the list of Holidays;                                                                                                                          
        // otherwise continue with previous table                                         
        DeleteHolidays = if Holidays = null then ListOfDates else List.Difference(ListOfDates, Holidays),
        // Select only the first 5 days of the week                                             
        // The 1 in the 2nd parameter of Date.DayOfWeek makes sure that Monday will be taken as first day of the week                                                                                                             
        DeleteWeekends = List.Select(DeleteHolidays, each Date.DayOfWeek(_, 1) < 5),
        // Count the number of days (items in the list)                                               
        CountDays =
            if Days >= 0 then
                DeleteWeekends{Days}
            else
                DeleteWeekends{List.Count(DeleteWeekends) + Days},
        //   CountDays = if Days >= 0 then List.Last(DeleteHolidays) else List.First(DeleteHolidays),                                                                                             
        Result = if CountDays = null then StartDate else CountDays
    in
        Result ,
    documentation = [
    Documentation.Name =  " Xls_WORKDAY ",
    Documentation.Description = " Returns a number that represents a date that is the indicated number of working days before or after a date (the starting date). ",
    Documentation.LongDescription = " Returns a number that represents a date that is the indicated number of working days before or after a date (the starting date). Working days exclude weekends and any dates identified as holidays. ",
    Documentation.Category = " Xls.Date ",
    Documentation.Source = " www.TheBIcountant.com - https://wp.me/p6lgsG-2sW ",
    Documentation.Version = " 1.0 ",
    Documentation.Author = " Imke Feldmann ",
    Documentation.Examples = {[Description =  "  ",
    Code = " let
        StartDate = #date(2008, 10, 1),
        Days = 151,
        Holidays = {#date(2008,11,26), #date(2008,12,4), #date(2009,1,21)},
        Result = Xls_WORKDAY(StartDate, Days, Holidays)
        
    in
        Result ",
    Result = " #date(2009,5,5) 
      "]}]
     in  
      Value.ReplaceType(func, Value.ReplaceMetadata(Value.Type(func), documentation))  