Hi Team, I have been given a project to work on that calculates the originial planned duration of a task and the actual time it took to complete the task.   For instance if a task n is planned to t...
  • Anonymous's avatar
    Anonymous
    1 year ago

    Hi maxkhan ,
    Thank you for your response. Below is a detailed overview for your reference.
    Add a New Column for the Actual Start Time of the Task

    • Open Power BI Desktop and load your dataset,In the Power Query Editor go to the Add Column tab
    • In dialog box, givea name to the new column . For example, enter ActualStartTime as the column name.
    • In the formula area,enter the below code

    = [ShiftStartTime] + #duration(0, 0, [ActualStartTimeOffset], 0)

     

    Add a New Column for the Actual Duration of the Task

    • Again, go to the Add Column tab. Click on Custom Column, name new column as ActualDuration.
    • Use the following formula to calculate the duration in hours

    = Duration.TotalHours([ActualEndTime] - [ActualStartTime])

     

    Convert the Duration to an Integer Value

    •  Go to the Add Column tab. Click on Custom Column.
    • Name the new column as Duration In Integer.
    • Use the below query

    = Number.RoundDown([ActualDuration])

    Hope the steps provided will be helpful in guiding you to create custom columns.If so,

    please consider marking Accept as solution to assist other members in finding it more easily.