3 years agocalculate date without holidays (only working days)
Good night After trying for several hours I had no choice but to resort to your help I have the following challenge, I have a table with a date to which I have to add a number of days based on a co...
ronrsnfld
Super User
3 years agoI have a different algorithm to offer, but need you to answer two questions:
- What country are you dealing with so far as holidays are concerned?
- Are we to assume that Date of Departure + One Day = Date of Departure?
jcamilo1985
Helper III
3 years agofirst of all thank you very much ronrsnfld for coming to the solution of the thread
1 - holidays are for Colombia
2 - no, we start counting the days from the departure date.
I annex the table of holidays that I have, the real table is older
| holydays |
| 1/01/2023 |
| 7/01/2023 |
| 8/01/2023 |
| 9/01/2023 |
| 14/01/2023 |
| 15/01/2023 |
| 21/01/2023 |
| 22/01/2023 |
| 28/01/2023 |
| 29/01/2023 |
| 4/02/2023 |
| 5/02/2023 |
| 11/02/2023 |
| 12/02/2023 |
| 18/02/2023 |
| 19/02/2023 |
| 25/02/2023 |
| 26/02/2023 |
| 4/03/2023 |
| 5/03/2023 |
| 11/03/2023 |
| 12/03/2023 |
| 18/03/2023 |
| 19/03/2023 |
| 20/03/2023 |
| 25/03/2023 |
| 26/03/2023 |
| 1/04/2023 |
| 2/04/2023 |
| 6/04/2023 |
| 7/04/2023 |
| 8/04/2023 |
| 9/04/2023 |
| 15/04/2023 |
| 16/04/2023 |
| 22/04/2023 |
| 23/04/2023 |
| 29/04/2023 |
| 30/04/2023 |
| 1/05/2023 |
| 6/05/2023 |
| 7/05/2023 |
| 13/05/2023 |
| 14/05/2023 |
| 20/05/2023 |
| 21/05/2023 |
| 22/05/2023 |
| 27/05/2023 |
| 28/05/2023 |
| 3/06/2023 |
| 4/06/2023 |
| 10/06/2023 |
| 11/06/2023 |
| 12/06/2023 |
| 17/06/2023 |
| 18/06/2023 |
| 19/06/2023 |
| 24/06/2023 |
| 25/06/2023 |
| 1/07/2023 |
| 2/07/2023 |
| 3/07/2023 |
| 8/07/2023 |
| 9/07/2023 |
| 15/07/2023 |
| 16/07/2023 |
| 20/07/2023 |
| 22/07/2023 |
| 23/07/2023 |
| 29/07/2023 |
| 30/07/2023 |
| 5/08/2023 |
| 6/08/2023 |
| 7/08/2023 |
| 12/08/2023 |
| 13/08/2023 |
| 19/08/2023 |
| 20/08/2023 |
| 21/08/2023 |
| 26/08/2023 |
| 27/08/2023 |
| 2/09/2023 |
| 3/09/2023 |
| 9/09/2023 |
| 10/09/2023 |
| 16/09/2023 |
| 17/09/2023 |
| 23/09/2023 |
| 24/09/2023 |
| 30/09/2023 |
| 1/10/2023 |
| 7/10/2023 |
| 8/10/2023 |
| 14/10/2023 |
| 15/10/2023 |
| 16/10/2023 |
| 21/10/2023 |
| 22/10/2023 |
| 28/10/2023 |
| 29/10/2023 |
| 4/11/2023 |
| 5/11/2023 |
| 6/11/2023 |
| 11/11/2023 |
| 12/11/2023 |
| 13/11/2023 |
| 18/11/2023 |
| 19/11/2023 |
| 25/11/2023 |
| 26/11/2023 |
| 2/12/2023 |
| 3/12/2023 |
| 8/12/2023 |
| 9/12/2023 |
| 10/12/2023 |
| 16/12/2023 |
| 17/12/2023 |
| 23/12/2023 |
| 24/12/2023 |
| 25/12/2023 |
| 30/12/2023 |
| 31/12/2023 |
- ronrsnfld3 years ago
Super User
Thank you.
- Generate a calender including the possible date range from which holidays and weekend days are removed.
- To add working days, we merely look for the position in the List of working days that corresponds to then number of working days you wish to add.
- In your specific case, since the departure date is counted as Day 1, you must subtract 1 from the number of days you are looking for.
- Note that in the code below, I took your list of holidays and put in in a Query named HolyDay for access. But there is also code commented out that can download the holiday list for many countries from the web. (Using a Table for this will be much faster, however.
- I don't know if you will run into the same problem you had with the other solution
//Note optional Holidays parameter //You can substitute a self-generated List of holidays, or use the website in the code to download a list // If you use the website, be sure to use a recognized country name //If you are using holidays, you should separate this list and buffer the result for speed issues. // as written, it will download this list every time the function executes (start as datetime, numDays as number, optional Country as nullable text) => let adjNumDays = Number.RoundAwayFromZero(Number.Abs(numDays*7/5))*2, yrStart = Date.Year(start), yrEnd = Date.Year(Date.AddDays(start,adjNumDays*Number.Sign(numDays))), //Create list of country specific Holidays holidays = HolyDays[holydays], /*yrs = {List.Min({yrEnd,yrStart})..List.Max({yrEnd,yrStart})}, if Country = null then {} else List.Accumulate(yrs,{},(state,current) => let Source=Web.Page(Web.Contents("https://www.officeholidays.com/countries/" & Country & "/" & Number.ToText(current))), Data0 = Source{0}[Data], DateCol = Table.SelectColumns(Data0,"Date"), fullDate = List.Transform(DateCol[Date], each Date.FromText(_ & " " & Number.ToText(current))) in state & fullDate),*/ //all Working dates //Generates a list of working dates in either Ascending or Descending order // based on the Sign of numDays // starting with the first working date after Start allWorkDates = List.RemoveNulls( List.Transform( List.DateTimes(start, adjNumDays, #duration(Number.Sign(numDays),0,0,0)), each if _ = start then _ else if Date.DayOfWeek(_)=Day.Saturday or Date.DayOfWeek(_)=Day.Sunday or List.Contains(holidays, Date.From(_)) then null else _)), addWorkDays = if numDays = 0 then start else allWorkDates{Number.Abs(numDays)} in addWorkDays