Project Online content pack for Power BI - health indicators

I am newly using the Project Online content pack for Power BI. In the health indicators (cost, work, schedule), I believe I've found information on the red, yellow, and green indicators. What do the gray indicators mean? I see them on projects that HAVE started. Thanks!
1 ACCEPTED SOLUTION
LDziubinski
New Member

Gray color means that projects do not have a written baseline. Therefore, the condition of the project can not be determined.

View solution in original post

3 REPLIES 3
NPBI
New Member

I do not have project online. But I would like to create excel data set locally using the project online data model so I can use power bi content pack developed for project online. Is there any sample content pack with off line excel data set? The reports in the content pack are very good to reuse locally.
LDziubinski
New Member

Gray color means that projects do not have a written baseline. Therefore, the condition of the project can not be determined.

v-yuezhe-msft
Employee
Employee

@CFlott,

I would recommend you connect to Project online pbit  file in Power BI Desktop, and then check how the indicators are defined in the report and what is the meaning of different colors.

Regards,
Lydia

Community Support Team _ Lydia Zhang
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

Helpful resources

Announcements
RTI Forums Carousel3

New forum boards available in Real-Time Intelligence.

Ask questions in Eventhouse and KQL, Eventstream, and Reflex.

LearnSurvey

Fabric certifications survey

Certification feedback opportunity for the community.

Top Solution Authors
Top Kudoed Authors