Project Online - Create Date for Baseline
Hi All,
I am using Power BI connected to Project Online to report on Project progress. I would like to start measuring/reporting on changes to the Project Finish date. The Finish Date does come through on the Project Baselines table however it is hard to map a nice visual trend as there appears to be no Baseline Create Date.
Assuming the Baseline Create date does exist in Project Online, does anyone know how you can pull this field through into Power BI?
Thanks,
Ashok
- Anonymous8 years ago
Ashok1,
You can add select query option in the OData URL, for more details, please review the following blog.
https://pwmather.wordpress.com/2013/08/01/projectserver-projectonline-highlight-report-example-ps2013-sp2013-excel-bi-office/
Regards,
Lydia
1 Reply
- AnonymousNot applicable
Ashok1,
You can add select query option in the OData URL, for more details, please review the following blog.
https://pwmather.wordpress.com/2013/08/01/projectserver-projectonline-highlight-report-example-ps2013-sp2013-excel-bi-office/
Regards,
Lydia