Need help on Calculation -

Hi All,

 

Quick help, please

 

In the client Cyrstal reporting system, the calculation was defined like this,

 

IF(IRD.RL_Date) = #12/07/2941 12:00:00 AM"# then 0 

else

Datediff("h",{IRD.Book_Date},{IRD.RL_Date})

 

Need your help in achieving the same condition in PowerBI? 

  • Hi Anonymous ,

     

    In M code, it would be something like this:

    if [IRD.RL_Date] = #datetime(2941, 07, 12, 00, 00, 00) then 0
    else Duration.Hours([IRD.RL_Date] - [IRD.Book_Date])

     

    Pete

2 Replies

  • Hi Anonymous ,

     

    In M code, it would be something like this:

    if [IRD.RL_Date] = #datetime(2941, 07, 12, 00, 00, 00) then 0
    else Duration.Hours([IRD.RL_Date] - [IRD.Book_Date])

     

    Pete

    • Anonymous's avatar
      Anonymous
      Not applicable

      Let me try this BA_Pete , Thanks for your update