Integrated Master Schedule to Powerbi

Hi, I have an integrated master schedule that I have stored on a SharePoint site. It is an MPP file. How do I connect this master schedule to powerbi?  I have heard to use Odata and I tried connecting as a sharepoint folder but I get errors. I am not sure what route is correct. 

 

Thank You, 

Marlene 

1 ACCEPTED SOLUTION
BA_Pete
Super User
Super User

Hi Marlene,

 

You can't connect to MPP files from Power BI (without an expensive connector). You'll need to get a Project Online licence and connect to the online version.

 

Pete



Now accepting Kudos! If my post helped you, why not give it a thumbs-up?

Proud to be a Datanaut!




View solution in original post

2 REPLIES 2
Anonymous
Not applicable

Thanks Pete.  I'll have to export to excel for now because I cannot get admin access to pull the odata from the pwa site.  work policies 

BA_Pete
Super User
Super User

Hi Marlene,

 

You can't connect to MPP files from Power BI (without an expensive connector). You'll need to get a Project Online licence and connect to the online version.

 

Pete



Now accepting Kudos! If my post helped you, why not give it a thumbs-up?

Proud to be a Datanaut!




Helpful resources

Announcements
Power BI DataViz World Championships

Power BI Dataviz World Championships

The Power BI Data Visualization World Championships is back! Get ahead of the game and start preparing now!

December 2025 Power BI Update Carousel

Power BI Monthly Update - December 2025

Check out the December 2025 Power BI Holiday Recap!

FabCon Atlanta 2026 carousel

FabCon Atlanta 2026

Join us at FabCon Atlanta, March 16-20, for the ultimate Fabric, Power BI, AI and SQL community-led event. Save $200 with code FABCOMM.