Integrated Master Schedule to Powerbi

Hi, I have an integrated master schedule that I have stored on a SharePoint site. It is an MPP file. How do I connect this master schedule to powerbi?  I have heard to use Odata and I tried connecting as a sharepoint folder but I get errors. I am not sure what route is correct. 

 

Thank You, 

Marlene 

1 ACCEPTED SOLUTION
BA_Pete
Super User
Super User

Hi Marlene,

 

You can't connect to MPP files from Power BI (without an expensive connector). You'll need to get a Project Online licence and connect to the online version.

 

Pete



Now accepting Kudos! If my post helped you, why not give it a thumbs-up?

Proud to be a Datanaut!




View solution in original post

2 REPLIES 2
Anonymous
Not applicable

Thanks Pete.  I'll have to export to excel for now because I cannot get admin access to pull the odata from the pwa site.  work policies 

BA_Pete
Super User
Super User

Hi Marlene,

 

You can't connect to MPP files from Power BI (without an expensive connector). You'll need to get a Project Online licence and connect to the online version.

 

Pete



Now accepting Kudos! If my post helped you, why not give it a thumbs-up?

Proud to be a Datanaut!




Helpful resources

Announcements
July PBI25 Carousel

Power BI Monthly Update - July 2025

Check out the July 2025 Power BI update to learn about new features.

Join our Fabric User Panel

Join our Fabric User Panel

This is your chance to engage directly with the engineering team behind Fabric and Power BI. Share your experiences and shape the future.

June 2025 community update carousel

Fabric Community Update - June 2025

Find out what's new and trending in the Fabric community.

Top Solution Authors