Hi, I have an integrated master schedule that I have stored on a SharePoint site. It is an MPP file. How do I connect this master schedule to powerbi? I have heard to use Odata and I tried connecting as a sharepoint folder but I get errors. I am not sure what route is correct.
Thank You,
Marlene
Solved! Go to Solution.
Hi Marlene,
You can't connect to MPP files from Power BI (without an expensive connector). You'll need to get a Project Online licence and connect to the online version.
Pete
Proud to be a Datanaut!
Thanks Pete. I'll have to export to excel for now because I cannot get admin access to pull the odata from the pwa site. work policies
Hi Marlene,
You can't connect to MPP files from Power BI (without an expensive connector). You'll need to get a Project Online licence and connect to the online version.
Pete
Proud to be a Datanaut!
Check out the September 2024 Power BI update to learn about new features.
Learn from experts, get hands-on experience, and win awesome prizes.
User | Count |
---|---|
72 | |
67 | |
42 | |
28 | |
21 |