Integrated Master Schedule to Powerbi
Hi, I have an integrated master schedule that I have stored on a SharePoint site. It is an MPP file. How do I connect this master schedule to powerbi? I have heard to use Odata and I tried connecting as a sharepoint folder but I get errors. I am not sure what route is correct.
Thank You,
Marlene
Hi Marlene,
You can't connect to MPP files from Power BI (without an expensive connector). You'll need to get a Project Online licence and connect to the online version.
Pete
2 Replies
- AnonymousNot applicable
Thanks Pete. I'll have to export to excel for now because I cannot get admin access to pull the odata from the pwa site. work policies
- BA_PeteSuper User
Hi Marlene,
You can't connect to MPP files from Power BI (without an expensive connector). You'll need to get a Project Online licence and connect to the online version.
Pete