Get Microsoft Project Unapproved Task and Unpublished Approved Task from Power BI

Hello!

 

I am trying to create a report in Power BI about how many tasks not yet approved by the status manager and how many tasks already approved but not yet published. Usually, I use OData to get data from Microsoft Project, but I can't find a table or field related to task approval. Does anyone know how to solve this problem?

 

Thanks and sorry for my bad English.

 

Regards,

Agung Santoso

2 REPLIES 2
v-eachen-msft
Community Support
Community Support

Hi @agungsantoso ,

 

1. Your URL may be incorrect, you could check it.

2. Your expected table may be a collection of multiple tables.

 

 

Community Support Team _ Eads
If this post helps, then please consider Accept it as the solution to help the other members find it.

Hi @v-eachen-msft,

 

Thanks for your reply, my OData connection is working well. I can get data from it. My problem is I can't find table/entities that has data about unapproved tasks or approved tasks but not yet published. I already find it in tasks, assignments table but it seems no data about it.

Helpful resources

Announcements
September Power BI Update Carousel

Power BI Monthly Update - September 2025

Check out the September 2025 Power BI update to learn about new features.

FabCon Atlanta 2026 carousel

FabCon Atlanta 2026

Join us at FabCon Atlanta, March 16-20, for the ultimate Fabric, Power BI, AI and SQL community-led event. Save $200 with code FABCOMM.