Formula Help! New Column (If this is not blank, use this, else)
Hello!! First time poster to this forum! HELPP.. I am struggling with this formula.. I have these three columns: Scheduled End Date Extended End Date Actual End Date It is like a...
Vijay_A_Verma
Most Valuable Professional
4 years agoUse this
= [Actual End Date]??[Extended End Date]??[Scheduled End Date]Anonymous
4 years agoNot applicable
thanks for your response! can you write it out completely?
- Vijay_A_Verma4 years ago
Most Valuable Professional
The above one is complete.
?? is Coalesce operator like other operators such as or, and etc..