Different days usinf custom column

Hi,

I'm using DirectQuery and i want to calculate the start date - end date without the weekend (Friday and Saturday) through a custom column. Can you help me?

  • Anonymous's avatar
    Anonymous
    2 years ago

    Hi Banan 

    When you use the calendar() funciton, then first date you need to input the start date, then second date you need to input the end date, the end date need to be greater than the start date, for the error message you offered , you didn't put the start date in the first date. You can refer to the following link.

    CALENDAR function (DAX) - DAX | Microsoft Learn

     

    Best Regards!

    Yolo Zhu

    If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

     

     

4 Replies

  • Anonymous's avatar
    Anonymous
    Not applicable

    Hi Banan 

    If you want to add the custom column in power query in direct query mode,  the custom column cannot be applied, becuse in direct mode, the steps in power query have limitations,you can refer to the following link.

    https://learn.microsoft.com/en-us/power-bi/connect-data/desktop-directquery-about#data-transformation-limitations.

    The direct mode have limitations in transform data and data modeling, you can refer to the following link.

    https://learn.microsoft.com/en-us/power-bi/connect-data/desktop-directquery-about#modeling-limitations

    The best way is to change the direct mode to import mode, then you can use the custom column, you can refer to the following sample.(the connect mode is import)

    Sample data 

    Add a custom column

     

    List.Sum(List.Transform(List.Dates([dt1],Duration.Days([dt2]-[dt1])+1,#duration(1,0,0,0)),each if Date.DayOfWeek(_,Day.Sunday)<5 then 1 else 0))

     

    Output

    If you cannot change the mode to import mode, please consider to create a measure, you can refer to the following measure.

     

    Measure =
    VAR a =
        ADDCOLUMNS (
            CALENDAR ( MIN ( SQLTest[dt1] ), MAX ( SQLTest[dt2] ) ),
            "Weekday", WEEKDAY ( [Date], 2)
        )
    RETURN
        COUNTROWS ( FILTER ( a, [Weekday] <> 5 && [Weekday] <> 6 ) )
    

     

    Output

    Best Regards!

    Yolo Zhu

    If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

     

     

     

    • Banan's avatar
      Banan
      Frequent Visitor

      There is no error in the code, but when I create a chart and use the new measure, this message appears " MdxScript(Model) (8,8) calculation error in measure "table name[Measure]: the start date in calender function can not be later than end date". 

      Note: The weekend in our country is Friday and Saturday

      • Anonymous's avatar
        Anonymous
        Not applicable

        Hi Banan 

        When you use the calendar() funciton, then first date you need to input the start date, then second date you need to input the end date, the end date need to be greater than the start date, for the error message you offered , you didn't put the start date in the first date. You can refer to the following link.

        CALENDAR function (DAX) - DAX | Microsoft Learn

         

        Best Regards!

        Yolo Zhu

        If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

         

         

    • Banan's avatar
      Banan
      Frequent Visitor

      There is no error in the code, but when I create a chart and use the new measure, this message appears " MdxScript(Model) (8,8) calculation error in measure "table name[Measure]: the start date in calender function can not be later than end date". 

      Note: The weekend in our country is Friday and Saturday