Dates Since last report

I have picked up a new Project management reporting tool that is based on PowerApps that then feeds into semantic models that I then report on in PowerBi, I am self-taught in PowerBi and PowerQuery, ...
  • MarkLaf's avatar
    5 months ago

    Since we're in the PQ forum, here is a solution with M. It looks a little crazy but should be relatively performant.

    let
        Source = sample,
        NewColType = [Dates since last report=[Type=Int64.Type,Optional=false]],
        Sort = Table.Sort(Source,{{"Project Name", Order.Ascending}, {"Report Date", Order.Ascending}}),
        Group = Table.Group(
            Sort, {"Project Name"}, {{
                "rows", each [
                    base = Table.Buffer( _ ), 
                    new_rows = List.Generate( 
                        ()=>0,each _<Table.RowCount(base),each _+1, 
                        each let current_row = base{_} in 
                        current_row & Record.FromList(
                            if _ = 0 then {null}
                                else let last_row = base{_-1} in
                                {Duration.Days( current_row[Report Date] - last_row[Report Date] )}, 
                            { Record.FieldNames( NewColType ){0} } 
                        ) 
                    ) 
                ] [ new_rows], 
                type list
            }}, 
            GroupKind.Local 
        ),
        ToTable = Table.FromRecords( 
            List.Combine( Group[rows] ), 
            type table Type.ForRecord( Type.RecordFields( Type.TableRow( Value.Type(Source) ) ) & NewColType, false)
        )
    in
        ToTable

     

    Tested with the below sample (generated with gemini):

    Sample (excerpt)

    Project Name Report Date Latest Report Days since report date
    Project A 2/24/2026 Yes 18
    Project A 2/18/2026 No 24
    Project A 1/9/2026 No 64
    Project A 1/2/2026 No 71
    Project A 10/9/2025 No 156
    Project A 9/30/2025 No 165
    Project B 12/15/2025 Yes 89
    Project B 12/12/2025 No 92
    Project C 1/12/2026 Yes 61
    Project C 12/4/2025 No 100
    Project C 10/12/2025 No 153
    Project C 10/2/2025 No 163
    Project C 9/15/2025 No 180
    ... ... ... ...
    Project BT 1/11/2026 Yes 62
    Project BT 12/6/2025 No 98
    Project BU 1/8/2026 Yes 65
    Project BU 1/6/2026 No 67
    Project BV 2/20/2026 Yes 22
    Project BV 1/3/2026 No 70
    Project BV 1/1/2026 No 72
    Project BV 12/23/2025 No 81

     

    Output