Forum Discussion
Anonymous
7 years agoNot applicable
Date diff function is not recognising the date columns from the table
- 7 years ago
Hi Anonymous ,
One sample for your reference.
DURATION = DATEDIFF ( MAX ( 'Table'[sai_startdate] ), MAX ( 'Table'[sai_duedate] ), DAY )
SteveCampbell
7 years agoMemorable Member
If this is a measure, you need to give it some type of context. Right now, you are reffering to a whole column, so it does not know which value in the column to use.
If you plan on using this in a table or graph, using the function "Selectedvalue" will add the current context.
Try this:
DURATION =
DATEDIFF(
SELECTEDVALUE(sai_duedate) ,
SELECTEDVALUE(sai_startdate) ,
day
)- Anonymous7 years agoNot applicable
Thanks Steve , I want to apply it on row level . Will this work ?
- v-frfei-msft7 years agoCommunity Support
Hi Anonymous ,
One sample for your reference.
DURATION = DATEDIFF ( MAX ( 'Table'[sai_startdate] ), MAX ( 'Table'[sai_duedate] ), DAY )