Forum Discussion
RaymondNG
4 years agoFrequent Visitor
Calculate Days Between Tasks in a Project
I am trying to calculate how many days there are between the completion of one task and the start of another. Each project has tasks ranging in number from 1 to 14. I'm working with multiple projects...
mahoneypat
4 years agoMicrosoft Employee
Please clarify your needed logic, as you have some that are out of order. For example, for Project A, Task 7 starts before Task 6 ends.
Pat
- RaymondNG4 years agoFrequent Visitor
Here is some cleaned up data with corrected dates. I'm trying to figure out how many days pass between the end of one task and the start of the subsequent task for each project. I found DAX to calculate the total project time on a different community page. I tried adding another variable for the Task Name so it would calculate the days between each tasks for individual projects but it returned blanks (see below). I'm new to Power BI so I may be missing something.
Project Name Start Date Complete Date Task Name Project A 8/1/2021 8/14/2021 Task 1 Project A 8/20/2021 8/20/2021 Task 2 Project A 8/24/2021 8/24/2021 Task 3 Project A 9/1/2021 9/4/2021 Task 4 Project A 9/6/2021 9/15/2021 Task 5 Project A 10/7/2021 10/7/2021 Task 6 Project A 11/21/2021 11/21/2021 Task 7 Project A 12/17/2021 12/17/2021 Task 8 Project A 1/27/2022 1/27/2022 Task 9 Project A 2/14/2022 2/14/2022 Task 10 Project A 2/28/2022 3/3/2022 Task 11 Project A 3/4/2022 3/4/2022 Task 12 Project A 3/14/2022 3/14/2022 Task 13 Project A 3/16/2022 3/20/2022 Task 14 Project B 7/7/2021 7/9/2021 Task 1 Project B 7/20/2021 7/31/2021 Task 2 Project B 8/17/2021 8/17/2021 Task 3 Project B 8/20/2021 8/31/2021 Task 4 Project B 9/1/2021 9/15/2021 Task 5 Project B 9/30/2021 10/1/2021 Task 6 Project B 10/22/2021 10/31/2021 Task 7 Project C 8/18/2021 8/19/2021 Task 1 Project C 9/14/2021 10/20/2021 Task 2 Project C 1/4/2022 1/4/2022 Task 3 Project C 1/5/2022 1/5/2022 Task 4 Project C 1/6/2022 1/6/2022 Task 5 Project C 1/13/2022 1/13/2022 Task 6 Project C 1/19/2022 1/19/2022 Task 7 Project C 2/11/2022 2/11/2022 Task 8 Project C 2/25/2022 2/25/2022 Task 9 Project C 2/18/2022 2/18/2022 Task 10 Project C 2/28/2022 2/28/2022 Task 11 Project C 3/4/2022 3/4/2022 Task 12 Project C 3/21/2022 3/21/2022 Task 13 Project D 8/6/2021 8/6/2021 Task 1 Project D 8/17/2021 8/17/2021 Task 2 Project D 8/30/2021 8/30/2021 Task 3 Project D 9/1/2021 9/10/2021 Task 4 Project D 9/11/2021 10/1/2021 Task 5 Project D 10/14/2021 10/14/2021 Task 6 Project D 1/25/2022 1/28/2022 Task 7 Project D 1/30/2022 2/2/2022 Task 8 Project D 2/8/2022 2/15/2022 Task 9 Project D 2/16/2022 2/17/2022 Task 10 Project D 2/20/2022 2/28/2022 Task 11 Project D 3/1/2022 3/4/2022 Task 12 Project D 3/7/2022 3/7/2022 Task 13 Days Between Tasks =VAR Task = MAX(Project[Task Name])VAR Project = MAX(Project[Project Name])VAR _Start =MINX(FILTER(ALL(mavenlink__Mavenlink_Task__c),Project[Project Name] = Project &&Project[Task Name] = Task &&Project[Task Start Date].[Date] <> BLANK()),Project[Task Start Date].[Date])VAR _Finish =MAXX(FILTER(ALL(mavenlink__Mavenlink_Task__c),Project[Project Name] = Project &&Project[Task Name] = Task &&Project[Task Complete Date].[Date] <> BLANK()),Project[Task Complete Date].[Date])RETURNIF(ISBLANK(_Finish),BLANK(),DATEDIFF(_Start, _Finish, DAY))