Gantt 2.2.3 Hover - Can it be customized?

I created a chart using the free Microsoft 2.2.3 Gantt chart visual.  The data that I used only has a required date (start date) with only the tasks completed having an end date.  To display the data, I created a duration column.  The following is a sample dataset.

 

Project Turnover TaskDate Required (MM/DD/YYYY)Date Completed (MM/DD/YYYY)Status (Blank, WIP or Completed)
(N/A; WIP; Complete)
Task 13/5/20243/1/2024Complete
Task 23/5/20243/5/2024Complete
Task 33/5/20243/8/2024Complete
Task 44/2/2024 WIP
Task 56/1/2024  
Task 6  N/A
Task 77/1/2024 WIP

 

The chart itself looks correct but the hover is not reporting the data properly.  Please see the screenshot below.  I need to at a minimin suppress the End Data field, which is reflecting 1 day when the duration is actually negative.

 

Gantt 223 Hover.png

 

I have read and tried to implement quite a few post suggestions but nothing worked.

 

Is there away (maybe using Python) to display my own hover data fields?  Any suggestions are appreciated!!

2 REPLIES 2
Strongbuck
Helper I
Helper I

I just tried to see if I could setup the visual to use a custom tooltip page but it didn't work.  I guess even though the Gantt 2.2.3 visual is from Microsoft, they made it so you don't have too many option to customize the hover.
 
Here is the calculation I wrote.  The reason the data is negative is because the task was completed before it was due.
 
Duration No = SWITCH (TRUE(),
'All_Projects'[Date Required] <> Blank() && [Date Completed] <> Blank() && 'All_Projects'[Date Required] <> 'All_Projects'[Date Completed], DATEDIFF ('All_Projects'[Date Required],'All_Projects'[Date Completed],DAY),
'All_Projects'[Date Required] <> Blank() && 'All_Projects'[Date Required] = 'All_Projects'[Date Completed], 1,
'All_Projects'[Date Required] <> Blank() &&  [Date Completed] = Blank(), 1,
Blank()
)
I looked at the pricing for the xVjz version and it isn't cheap.  The Microsoft version is fine except for the hover.  We don't want to sprend money when it meets our needs on all of the other fronts.
 
Does anyone know if the Microsoft Gantt 2.2.3 is due for an upgrade?  Maybe they added additional options for the tooltip.  I'm sure I;m not the only one that as run into this issue.
Anonymous
Not applicable

Hi @Strongbuck ,

Base on your description, it seems that you’re experiencing issues with the duration being displayed incorrectly, it might be due to how the duration is being calculated. If the duration is negative, it might be worth checking the formula used to calculate the duration to ensure it’s correct. How did you set the Gantt visual? Could you please provide the related formula of calculating the duration?

 

In addition, please check if there are other Gantt chart visuals available in the Power BI marketplace that might offer more customization options. For example, 'Gantt Chart-xViz’ is one such visual that allows adjustments to be made.

Gantt Chart - xViz 

vyiruanmsft_0-1710148171780.png

Best Regards

Helpful resources

Announcements
Power BI DataViz World Championships

Power BI Dataviz World Championships

The Power BI Data Visualization World Championships is back! Get ahead of the game and start preparing now!

December 2025 Power BI Update Carousel

Power BI Monthly Update - December 2025

Check out the December 2025 Power BI Holiday Recap!

FabCon Atlanta 2026 carousel

FabCon Atlanta 2026

Join us at FabCon Atlanta, March 16-20, for the ultimate Fabric, Power BI, AI and SQL community-led event. Save $200 with code FABCOMM.