Hi caruso1058 - see this measure:
Finish Date = VAR varCurrentDate = MAX('Table'[Start_Date]) VAR varNextDate = CALCULATE( MIN('Table'[Start_Date]), FILTER( All('Table'), 'Table'[Start_Date] > varCurrentDate ) ) RETURN IF( ISBLANK(varNextDate), varCurrentDate, varNextDate )This will return the minium date above the current date, unless there is no next date, in which case it will repeat the current date.
One note caruso1058 - you didn't specify, but I assume you want this to be by project. Note the replacement of ALL() with ALLEXCEPT()
So you can see that the April 1, 2020 date did not impact the A123 project.
- 5 years ago
Hi,
Try this calculated column formula
=calculate(min(data[project schedule]),filter(data,data[project]=earlier(data[project])&&data[project schedule]>earlier(data[project schedule])))
Hope this helps.
edhans ,
I have watched a lot of Enterprise DNA videos in my DAX learning journey and they make the same case that, Measures are much more efficient compared to calcualted columns.
I will look into the resources you provided, to explore this further.
Thanks a bunch for your help!!
Glad to be of assistance caruso1058. Calculated Columns are very "Excel Like" so people jump on them, myself included in my early Power BI days.
But I've learned they should be avoided except in very specific use cases.