Forum Discussion
task utilization dashboard
- 5 years ago
Hi prinuce ,
According to your description, I am a little confused. If you want to make a Gantt, you may need to have a %completion
column and a duration column, so I first added two columns, and then added to the Gantt chart, I hope it will help you:
Step 1: Add column( %complete)% completion = IF('Sheet1 (2)'[Status]="In Progress",0.5,IF('Sheet1 (2)'[Status]="Complete",1,0))Add another column:
Duration = DATEDIFF('Sheet1 (2)'[Start Date],'Sheet1 (2)'[End Date],DAY)Step2:Add gantt visual
The final output is shown below:
Best Regards,
Yalan Wu
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.
Hi prinuce ,
According to your description, I am a little confused. If you want to make a Gantt, you may need to have a %completion
column and a duration column, so I first added two columns, and then added to the Gantt chart, I hope it will help you:
Step 1: Add column( %complete)
% completion = IF('Sheet1 (2)'[Status]="In Progress",0.5,IF('Sheet1 (2)'[Status]="Complete",1,0))Add another column:
Duration = DATEDIFF('Sheet1 (2)'[Start Date],'Sheet1 (2)'[End Date],DAY)Step2:Add gantt visual
The final output is shown below:
Best Regards,
Yalan Wu
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.