Hi,

 

For each 'MFG_ORDER_NAME' and 'OP_SEQ_NUMBER' and I need to calculatie the sum of 'RESOURCE_REQUIRED_AMOUNT' and sum of transaction quantity. The last one is easy and I do not need help with that.

The problem lies within the resource required amount. If 'RESOURCE_SEQ_NUMBER'= 20 AND 'BASIS' is "Lot", the sum within this example should be 160. For each transaction quantity row, the underlying table shows 160. If 'RESOURCE_SEQ_NUMBER' = 30 AND 'BASIS' is "Item", the sum should be the 810. This is the line qty of 270 * Order qty based in the table JOBS (linked but not shown here).

 

 

 

Thanks for any help!

  • Hi Anonymous

    Assume your data table(according to your screenshot)  is like

     

    If the table JOBS is like this, and there a relationship built between two tables (it is better to set cross filter direction "Both")

    ORDER_NAME qty
    1 3
    2 4
    3 5
    4 6
    5 7

     

    Then create a measure

    Measure = IF(MAX([col4])=20&&MAX([col5])="Lot",MAX([col6]),IF(MAX([col4])=30&&MAX([col5])="Item",MAX([col6])*MAX(Sheet12[qty])))

    Best Regards

    Maggie

4 Replies

  • v-juanli-msft's avatar
    v-juanli-msft
    Community Support

    Hi Anonymous

    Assume your data table(according to your screenshot)  is like

     

    If the table JOBS is like this, and there a relationship built between two tables (it is better to set cross filter direction "Both")

    ORDER_NAME qty
    1 3
    2 4
    3 5
    4 6
    5 7

     

    Then create a measure

    Measure = IF(MAX([col4])=20&&MAX([col5])="Lot",MAX([col6]),IF(MAX([col4])=30&&MAX([col5])="Item",MAX([col6])*MAX(Sheet12[qty])))

    Best Regards

    Maggie

    • Anonymous's avatar
      Anonymous
      Not applicable

      Thanks Maggie. Problem solved!

      • Anonymous's avatar
        Anonymous
        Not applicable

        Now the individual lines are correct but the sum of 'RESOURCE_REQUIRED_AMOUNT' is incorrect, which now is 13.5

        This should be 32.85. I used following calculation.

         

        Hrs_routing = IF(MAX(XXBI_MFG_RESOURCE_TXNS_V[RESOURCE_SEQUENCE_NUMBER])=20 && MAX(XXBI_MFG_RESOURCE_TXNS_V[BASIS])="Lot",max(XXBI_MFG_RESOURCE_TXNS_V[RESOURCE_REQUIRED_AMOUNT])/60,(MAX(XXBI_WIP_JOBS_V[QUANTITY_COMPLETED])*MAX(XXBI_MFG_RESOURCE_TXNS_V[RESOURCE_REQUIRED_AMOUNT]))/60)