project online custom fields
Hi Anonymous,
Based on test, default project connector can't access to custom fields.
Please use odata connector with project online rest api to get custom fields.
Reference link:
Regards,
Xiaoxin Sheng
- Anonymous7 years agoNot applicable
Bringing this post back from the dead.
Did anyone figure out how to use Project custom fields in power bi?
- echristoph7 years agoHelper I
Attempting to use the rest API when retrieving enterprise custom field for tasks gets the following error:
DataSource.Error: We couldn't parse OData response result. Error: A value without a type name was found and no expected type is available. When the model is specified, each value in the payload must have a type which can be either specified in the payload, explicitly by the caller or implicitly inferred from the parent value.
This is because the custom fields come back like this when you perform a REST query to Project Online:
<content type="application/xml"> <m:properties> <d:Id m:type="Edm.Guid">83e390a8-d357-e911-afb5-00155d0c6b26</d:Id> <d:OutlinePosition>2</d:OutlinePosition> <d:ActualFinish m:type="Edm.DateTime">0001-01-01T00:00:00</d:ActualFinish> <d:ActualStart m:type="Edm.DateTime">0001-01-01T00:00:00</d:ActualStart> <d:Cost m:type="Edm.Double">13591.68</d:Cost> <d:Duration>4d</d:Duration> <d:Finish m:type="Edm.DateTime">2019-04-10T17:00:00</d:Finish> <d:IsActive m:type="Edm.Boolean">true</d:IsActive> <d:Name>Develop Analysis of Alternatives (AoA) Study Guidance</d:Name> <d:OutlineLevel m:type="Edm.Int32">1</d:OutlineLevel> <d:PercentComplete m:type="Edm.Int32">0</d:PercentComplete> <d:PercentPhysicalWorkComplete m:type="Edm.Int32">0</d:PercentPhysicalWorkComplete> <d:RemainingDuration>4d</d:RemainingDuration> <d:Start m:type="Edm.DateTime">2019-04-05T08:00:00</d:Start> <d:Work>160h</d:Work> <d:Custom_x005f_90eaefb93561e911afb900155d0c3815 m:type="Collection(Edm.String)"> <d:element>Entry_da588e9e3561e911afb900155d0c3815</d:element> </d:Custom_x005f_90eaefb93561e911afb900155d0c3815> /m:properties> </content>Notice the <d:element> tag does not have an "m:type" attribute; I think this is confusing PowerBI.
You can try it yourself:
https://[yourtenant].sharepoint.com/sites/[yoursite]/_api/ProjectServer/Projects('[projectGUID]')/Tasks('[taskGUID]')
This will work in a browser URL (assuming you are logged in), but will error in Power BI.
Any ideas how to workaround? If I could retrieve the element value into PowerBI I can relate it to the Lookup Table.
P.S. I don't know how to escape the stupid emoticons in the code block, sorry.- echristoph7 years agoHelper I
OK, I figured it out. You can't get them using the OData connector, but you CAN do it with the XML reader. Example:
Source = Xml.Tables(Web.Contents("https://[yourtenant].sharepoint.com/sites/[yoursite]/_api/ProjectServer/Projects?" & "$expand=Tasks&$select=Id" & ",Tasks/Id" & ",Tasks/OutlineLevel" & ",Tasks/OutlinePosition" & ",Tasks/Name" & ",Tasks/Start" & ",Tasks/Finish" & ",Tasks/ActualStart" & ",Tasks/ActualFinish" & ",Tasks/PercentComplete" & ",Tasks/PercentPhysicalWorkComplete" & ",Tasks/Duration" & ",Tasks/RemainingDuration" & ",Tasks/Work" & ",Tasks/Cost" & ",Tasks/IsActive" & ",Tasks/Custom_x005f_90eaefb93561e911afb900155d0c3815" &
",Tasks/Custom_x005f_1a9572776960e9119487283a4d07a952" &
",Tasks/Custom_x005f_351797c94968e911b07700155d10a106" &
",Tasks/Custom_x005f_c4f66ed64968e911b07700155d10a106" &
",Tasks/Custom_x005f_d3dfad7fa85fe911afb800155d10502b"))Notice the Tasks/Custom_x005f_xxxxxxxx. Those are enterprise custom field lookup entries associated with that task. You can pull their values from the Enterprise Lookup tables and relate them in Power BI. Solved!
- chowdarygm6 years agoFrequent Visitor
echristoph wrote:OK, I figured it out. You can't get them using the OData connector, but you CAN do it with the XML reader. Example:
Source = Xml.Tables(Web.Contents("https://[yourtenant].sharepoint.com/sites/[yoursite]/_api/ProjectServer/Projects?" & "$expand=Tasks&$select=Id" & ",Tasks/Id" & ",Tasks/OutlineLevel" & ",Tasks/OutlinePosition" & ",Tasks/Name" & ",Tasks/Start" & ",Tasks/Finish" & ",Tasks/ActualStart" & ",Tasks/ActualFinish" & ",Tasks/PercentComplete" & ",Tasks/PercentPhysicalWorkComplete" & ",Tasks/Duration" & ",Tasks/RemainingDuration" & ",Tasks/Work" & ",Tasks/Cost" & ",Tasks/IsActive" & ",Tasks/Custom_x005f_90eaefb93561e911afb900155d0c3815" &
",Tasks/Custom_x005f_1a9572776960e9119487283a4d07a952" &
",Tasks/Custom_x005f_351797c94968e911b07700155d10a106" &
",Tasks/Custom_x005f_c4f66ed64968e911b07700155d10a106" &
",Tasks/Custom_x005f_d3dfad7fa85fe911afb800155d10502b"))Notice the Tasks/Custom_x005f_xxxxxxxx. Those are enterprise custom field lookup entries associated with that task. You can pull their values from the Enterprise Lookup tables and relate them in Power BI. Solved!
echristoph How did you connect the tasks site to XML? any pointers is appreciated.