networkingdays with [Year] option
- 3 years ago
Hi lastnn30 ,
in the function NETWORKDAYS the third and forth parameter are optional. Why do you use the dot after [Date2] and not the comma? If you use the comma you should see the correct syntax that is:
NETWORKDAYS(<start_date>,<end_date> [,<weekend>] [,<holidays>])
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.
Hi lastnn30 ,
in the function NETWORKDAYS the third and forth parameter are optional. Why do you use the dot after [Date2] and not the comma? If you use the comma you should see the correct syntax that is:
NETWORKDAYS(<start_date>,<end_date> [,<weekend>] [,<holidays>])