Hi All,
I need help with my problem, thanks before.
I have problem with making chart over due days that automatically change based on selected slicer date (using Before function)
here is my excel table looks like
Invoice | Customer | Transaction Date | Due Date | Overdue Date | Value |
INV001 | Akai | 4/22/2022 | 4/30/2022 | 182 | 1,000.00 |
INV002 | Bim | 4/22/2022 | 4/30/2022 | 182 | 1,500.00 |
INV003 | Della | 4/22/2022 | 4/30/2022 | 182 | 1,000.00 |
INV004 | Akai | 4/22/2022 | 4/30/2022 | 182 | 6,000.00 |
INV005 | Akai | 4/22/2022 | 4/30/2022 | 182 | 75,000.00 |
INV006 | Cerry | 6/29/2022 | 7/7/2022 | 114 | 2,500.00 |
INV007 | Foam | 6/29/2022 | 7/7/2022 | 114 | 8,000.00 |
INV008 | Della | 6/29/2022 | 7/7/2022 | 114 | 8,500.00 |
INV009 | Cerry | 9/22/2022 | 9/30/2022 | 29 | 2,500.00 |
INV010 | Gero | 9/22/2022 | 9/30/2022 | 29 | 1,300.00 |
INV011 | Ian | 9/22/2022 | 9/30/2022 | 29 | 1,325.00 |
INV012 | Ian | 9/22/2022 | 9/30/2022 | 29 | 4,600.00 |
INV013 | Gero | 10/21/2022 | 10/29/2022 | 0 | 4,500.00 |
INV014 | Della | 10/21/2022 | 10/29/2022 | 0 | 5,500.00 |
INV015 | Foam | 10/22/2022 | 10/30/2022 | -1 | 10,250.00 |
INV016 | Foam | 11/24/2022 | 12/2/2022 | -34 | 15,000.00 |
INV017 | Foam | 11/24/2022 | 12/2/2022 | -34 | 16,000.00 |
INV018 | Cerry | 11/24/2022 | 12/2/2022 | -34 | 25,000.00 |
INV019 | Cerry | 11/26/2022 | 12/4/2022 | -36 | 17,500.00 |
INV020 | Gero | 11/26/2022 | 12/4/2022 | -36 | 90,000.00 |
Slicer Filter date that I choose : 10/29/2022
expected Matrix table that I need looks like this
Customer | Total Value | < 1 day | 1 - 30 days | 31 - 60 days | > 60 days |
Akai | 82,000.00 | 0 | 0 | 0 | 82,000.00 |
Bim | 1500 | 0 | 0 | 0 | 1,500.00 |
Cerry | 47,500.00 | 42,500.00 | 2,500.00 | 0 | 2,500.00 |
Della | 15,000.00 | 5,500.00 | 0 | 0 | 9,500.00 |
Foam | 49,250.00 | 41,250.00 | 0 | 0 | 8,000.00 |
Gero | 95,800.00 | 94,500.00 | 1,300.00 | 0 | 0 |
Ian | 5,925.00 | 0 | 5,925.00 | 0 | 0 |
TOTAL | 296,975.00 | 183,750.00 | 9,725.00 | - | 103,500.00 |
I already find the solution if the Slicer date = Today,
But I cannot find the solution if the slicer date is changeable to different date and the Over Due will follow the different between due date and slicer date
Please help me. thank you
Solved! Go to Solution.
Hi @tevisyauw ,
According to your description, here's my solution.
1.Create a table to list all the ranges, then sort the Range column by Sort column.
2.Create two measures.
Measure1 =
IF (
HASONEVALUE ( 'Table'[Invoice] ),
MAX ( 'Table'[Value] ),
SUMX ( 'Table', 'Table'[Value] )
)
Measure2 =
SWITCH (
MAX ( 'Range'[Range] ),
"Total Value", SUM ( 'Table'[Value] ),
"< 1 day",
CALCULATE (
[Measure1],
DATEDIFF ( 'Table'[Due Date], SELECTEDVALUE ( 'Date'[Date] ), DAY ) < 1
) + 0,
"1 - 30 days",
CALCULATE (
[Measure1],
DATEDIFF ( 'Table'[Due Date], SELECTEDVALUE ( 'Date'[Date] ), DAY ) >= 1,
DATEDIFF ( 'Table'[Due Date], SELECTEDVALUE ( 'Date'[Date] ), DAY ) <= 30
) + 0,
"31 - 60 days",
CALCULATE (
[Measure1],
DATEDIFF ( 'Table'[Due Date], SELECTEDVALUE ( 'Date'[Date] ), DAY ) >= 31,
DATEDIFF ( 'Table'[Due Date], SELECTEDVALUE ( 'Date'[Date] ), DAY ) <= 60
) + 0,
"> 60 days",
CALCULATE (
[Measure1],
DATEDIFF ( 'Table'[Due Date], SELECTEDVALUE ( 'Date'[Date] ), DAY ) > 60
) + 0
)
Put Customer in Matrix Rows, Range in Columns and the new Measure2 in Values, get the correct result:
It can dynamically change by the selected value in Date slicer.
I attach my sample below for your reference.
Best Regards,
Community Support Team _ kalyj
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.
Hi @tevisyauw ,
According to your description, here's my solution.
1.Create a table to list all the ranges, then sort the Range column by Sort column.
2.Create two measures.
Measure1 =
IF (
HASONEVALUE ( 'Table'[Invoice] ),
MAX ( 'Table'[Value] ),
SUMX ( 'Table', 'Table'[Value] )
)
Measure2 =
SWITCH (
MAX ( 'Range'[Range] ),
"Total Value", SUM ( 'Table'[Value] ),
"< 1 day",
CALCULATE (
[Measure1],
DATEDIFF ( 'Table'[Due Date], SELECTEDVALUE ( 'Date'[Date] ), DAY ) < 1
) + 0,
"1 - 30 days",
CALCULATE (
[Measure1],
DATEDIFF ( 'Table'[Due Date], SELECTEDVALUE ( 'Date'[Date] ), DAY ) >= 1,
DATEDIFF ( 'Table'[Due Date], SELECTEDVALUE ( 'Date'[Date] ), DAY ) <= 30
) + 0,
"31 - 60 days",
CALCULATE (
[Measure1],
DATEDIFF ( 'Table'[Due Date], SELECTEDVALUE ( 'Date'[Date] ), DAY ) >= 31,
DATEDIFF ( 'Table'[Due Date], SELECTEDVALUE ( 'Date'[Date] ), DAY ) <= 60
) + 0,
"> 60 days",
CALCULATE (
[Measure1],
DATEDIFF ( 'Table'[Due Date], SELECTEDVALUE ( 'Date'[Date] ), DAY ) > 60
) + 0
)
Put Customer in Matrix Rows, Range in Columns and the new Measure2 in Values, get the correct result:
It can dynamically change by the selected value in Date slicer.
I attach my sample below for your reference.
Best Regards,
Community Support Team _ kalyj
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.
Thank you @v-yanjiang-msft , it worked like a magic. I just tweak it a little on Selected date from
SELECTEDVALUE ( 'Date'[Date] )
to
LASTDATE( 'Date'[Date] )
because I'm using date slicer type Before
need help. from anyone. the empty cell was 0 value. got auto formatted from excel
Starting December 3, join live sessions with database experts and the Fabric product team to learn just how easy it is to get started.
March 31 - April 2, 2025, in Las Vegas, Nevada. Use code MSCUST for a $150 discount! Early Bird pricing ends December 9th.
User | Count |
---|---|
94 | |
90 | |
84 | |
70 | |
49 |
User | Count |
---|---|
143 | |
121 | |
112 | |
59 | |
58 |