Hello all,

 

I’ve been struggling all day on this and can’t find a solution.

I’m trying to work out how many workers my factory needs in the future.  I have a total each week that we need, [Weeks backlog efficiency Zoned] and a running total of the number of workers needed [Cumulative], but I want to minus off each value the number of workers we have [Past Staff] .  because we are behind I need to have a cumulative total and move what’s left to be made over into spare capacity next week ect hence the running total.

 

Cumulative =

CALCULATE([Weeks backlog efficiency Zoned],

   FILTER(ALL('Future Orders'[Yearweek Backlog 2-5]),VALUE('Future Orders'[Yearweek Backlog 2-5]) <= VALUE(MAX('Future Orders'[Yearweek Backlog 2-5]))))

 

When I minus off the number of workers [paststaff] it only takes it off the first week not every week so I end up with a growing number

 

 

 

5 Replies

    • Anonymous's avatar
      Anonymous
      Not applicable

      Hi thanks for the reply. I think your right about the scope, however even if I type in minus 7 it only takes it off the first week so I need to write something that repeats the process.  the past staff formula is below, it simply works out the full time days worked including overtime over the last 5 weeks.   Labour(2) is not linked to the date that the rest of the sheet uses. 

       

      "PastStaff= (
      IF('D Labour (2)'[Time period]="last5week",
      IF('D Labour (2)'[Type of work] = "NoOfHeads",'D Labour (2)'[Value]*8,
      IF('D Labour (2)'[Type of work]="Hrs Overtime",'D Labour (2)'[Value],0)
      ))/5)/37"
  • Anonymous's avatar
    Anonymous
    Not applicable

    I have made a cumulative Colum of the Work which needs doing:

    Cummulative work =

    (CALCULATE([Weeks backlog efficiency Zoned]    ,

        FILTER(ALL('Future Orders'[Yearweek Backlog 2-5]),VALUE('Future Orders'[Yearweek Backlog 2-5]) <= VALUE(MAX('Future Orders'[Yearweek Backlog 2-5])))))

     

    and the difference between the Labour we have and the Labour we need:

     

    +/- staff = [Weeks backlog efficiency Zoned]-SUM('D Labour (2)'[Past Staff])

     

    this sits nicely in each “Yearweek Backlog 2-5”.  now all I need is a cumulative total of the +/-staff but it doesn’t work :(

     