Hi All I am going crazy here with this measure, but i need it to calculate
if due date is +1 day over submit date, it is working currently with on time or late but showing data as late if submitted on the due date. Hope this makes sense 🙄
The below is showing late but infact it is on time submitted.
Many thanks
James
Solved! Go to Solution.
Hello @JamesMurg ,
adjust your measure to submission[duedate] >=
If I answered your question, please mark my post as solution, Appreciate your Kudos 👍
Proud to be a Super User! | |
Hello @JamesMurg ,
adjust your measure to submission[duedate] >=
If I answered your question, please mark my post as solution, Appreciate your Kudos 👍
Proud to be a Super User! | |
Many thanks 😀
Starting December 3, join live sessions with database experts and the Fabric product team to learn just how easy it is to get started.
March 31 - April 2, 2025, in Las Vegas, Nevada. Use code MSCUST for a $150 discount! Early Bird pricing ends December 9th.
User | Count |
---|---|
94 | |
90 | |
84 | |
70 | |
49 |
User | Count |
---|---|
141 | |
121 | |
112 | |
59 | |
58 |