Hi All I am going crazy here with this measure, but i need it to calculate

if due date is +1 day over submit date, it is working currently with on time or late but showing data as late if submitted on the due date.  Hope this makes sense 🙄

 

JamesMurg_0-1683797261265.png

The below is showing late but infact it is on time submitted.

JamesMurg_1-1683797360836.png

JamesMurg_2-1683797394476.png

 

Many thanks

James

 

 

 

1 ACCEPTED SOLUTION
Idrissshatila
Super User
Super User

Hello @JamesMurg ,

 

adjust your measure to submission[duedate] >= 


If I answered your question, please mark my post as solution, Appreciate your Kudos 👍

Follow me on Linkedin



Did I answer your question? Mark my post as a solution! Appreciate your Kudos
Follow me on LinkedIn linkedIn
Vote for my Community Mobile App Idea

Proud to be a Super User!




View solution in original post

2 REPLIES 2
Idrissshatila
Super User
Super User

Hello @JamesMurg ,

 

adjust your measure to submission[duedate] >= 


If I answered your question, please mark my post as solution, Appreciate your Kudos 👍

Follow me on Linkedin



Did I answer your question? Mark my post as a solution! Appreciate your Kudos
Follow me on LinkedIn linkedIn
Vote for my Community Mobile App Idea

Proud to be a Super User!




Many thanks 😀

Helpful resources

Announcements
Feb2025 Sticker Challenge

Join our Community Sticker Challenge 2025

If you love stickers, then you will definitely want to check out our Community Sticker Challenge!

Jan NL Carousel

Fabric Community Update - January 2025

Find out what's new and trending in the Fabric community.