So here you go:
Budget phase = CALCULATE(sum('public budget'[Heures prévus]),FILTER('public budget','public budget'[Phase de projet]=RELATED('public financial-overview'[Phase par défaut])))
https://drive.google.com/drive/folders/1J8l7Ahx0m7ZXlAMMKAhFu4MDN9L9FljO?usp=sharing
Here is the file
Anonymous Kudos means thumbs up only.
BTW, is that solution working?
- Tahreem246 years ago
Super User
Anonymous ,
Please verify the below Screen shot. If not correct so kindly share the expected output for Budget Phase.
- Anonymous6 years agoNot applicable
Tahreem24 : what i am expecting to have is the following :
For each project code, there is a current phasis (contained in field "phase par défaut" in "Public financial-overview" table.
In the table "Budget", i have to sum "Heures prévus" for each row whare the field "phase de projet" is equal to "phase par défaut".
So doing like this, i have the budget in hours for the current phasis of the project.
- Tahreem246 years ago
Super User
Anonymous ,
Validate the below Screen shot: