I have a data table that contains a Start Date and I want a column called Target Date which is 30 working days from the Start Date. I also have a calendar table which I can connect to the Start Date if needed.
Can someone help with the DAX for the column or M Code if I need to do this in Power Query? Can I also have the option to put Holidays in ie Christmas Day, New Years day etc.
Many thanks
@tamerj1 @amitchandak @parry2k @Anonymous
@spandy34 maybe you also want to check this video on my YT channel How to calculate shipping date based on the working date ignore non working days - Power BI - YouTub...
Subscribe to the @PowerBIHowTo YT channel for an upcoming video on List and Record functions in Power Query!!
Learn Power BI and Fabric - subscribe to our YT channel - Click here: @PowerBIHowTo
If my solution proved useful, I'd be delighted to receive Kudos. When you put effort into asking a question, it's equally thoughtful to acknowledge and give Kudos to the individual who helped you solve the problem. It's a small gesture that shows appreciation and encouragement! ❤
Did I answer your question? Mark my post as a solution. Proud to be a Super User! Appreciate your Kudos 🙂
Feel free to email me with any of your BI needs.
@spandy34 Yes whatever column is used for the start date.
Subscribe to the @PowerBIHowTo YT channel for an upcoming video on List and Record functions in Power Query!!
Learn Power BI and Fabric - subscribe to our YT channel - Click here: @PowerBIHowTo
If my solution proved useful, I'd be delighted to receive Kudos. When you put effort into asking a question, it's equally thoughtful to acknowledge and give Kudos to the individual who helped you solve the problem. It's a small gesture that shows appreciation and encouragement! ❤
Did I answer your question? Mark my post as a solution. Proud to be a Super User! Appreciate your Kudos 🙂
Feel free to email me with any of your BI needs.
@spandy34 try this, add new column:
Target Date =
VAR __TargetDays = 30
VAR __StartDate = Table[Start Date]
VAR __TargetDate = __StartDate + __TargetDays
VAR __TargetDateWeekDay = WEEKDAY ( __TargetDate, 3 )
VAR __AddDays = IF ( __TargetDateWeekDay IN { 5, 6 }, 7 - __TargetDateWeekDay, 0 )
VAR __TargetWorkingDate = __TargetDate + __AddDays
RETURN __TargetWorkingDate
Subscribe to the @PowerBIHowTo YT channel for an upcoming video on List and Record functions in Power Query!!
Learn Power BI and Fabric - subscribe to our YT channel - Click here: @PowerBIHowTo
If my solution proved useful, I'd be delighted to receive Kudos. When you put effort into asking a question, it's equally thoughtful to acknowledge and give Kudos to the individual who helped you solve the problem. It's a small gesture that shows appreciation and encouragement! ❤
Did I answer your question? Mark my post as a solution. Proud to be a Super User! Appreciate your Kudos 🙂
Feel free to email me with any of your BI needs.
Thank you for responding. So I have put the following in the column but it is calculating 30 days and including weekends. Is the Date in line 3 supposed to be from my date table or as outlined below, from the Caseload Oversight'[ASMStartDate] field?