KG1 , Try a new column like
business Day = COUNTROWS(FILTER(ADDCOLUMNS(CALENDAR(Table[Onsite_Date],Table[Completion Date]),"WorkDay", if(WEEKDAY([Date],2) <6,1,0)),[WorkDay] =1))
How to calculate Business Days/ Workdays, with or without date table: https://youtu.be/Qv4wT8_P-AA
KG1 , Try a new column like
business Day = COUNTROWS(FILTER(ADDCOLUMNS(CALENDAR(Table[Onsite_Date],Table[Completion Date]),"WorkDay", if(WEEKDAY([Date],2) <6,1,0)),[WorkDay] =1))
How to calculate Business Days/ Workdays, with or without date table: https://youtu.be/Qv4wT8_P-AA
- KG14 years agoResolver I
Hi Apologies but I get the following error message
The start date in Calendar function can not be later than the end date.
- amitchandak4 years agoSuper User
KG1 , Make sure the first date is a smaller one
business Day = if(Table[Onsite_Date] < Table[Completion Date] , COUNTROWS(FILTER(ADDCOLUMNS(CALENDAR(Table[Onsite_Date],Table[Completion Date]),"WorkDay", if(WEEKDAY([Date],2) <6,1,0)),[WorkDay] =1)),
COUNTROWS(FILTER(ADDCOLUMNS(CALENDAR(Table[Completion Date],Table[Onsite_Date]),"WorkDay", if(WEEKDAY([Date],2) <6,1,0)),[WorkDay] =1)))