Forum Discussion
Weeks Duration
- 6 years ago
Try
link : https://www.dropbox.com/s/9jelo8gddv88sq0/Week%20start%20end%20Monday.pbix?dl=0
Week Start date = 'Table'[Date]-1*WEEKDAY('Table'[Date],2)+1 Week End date = 'Table'[Date]+7-1*WEEKDAY('Table'[Date],2) Week of = FORMAT('Table'[Week Start date],"dd/mm/yyyy") & " "& FORMAT('Table'[Week End date],"dd/mm/yyyy")Appreciate your Kudos. In case, this is the solution you are looking for, mark it as the Solution. In case it does not help, please provide additional information and mark me with @
Thanks. My Recent Blog -
Winner-Topper-on-Map-How-to-Color-States-on-a-Map-with-Winners , HR-Analytics-Active-Employee-Hire-and-Termination-trend
Power-BI-Working-with-Non-Standard-Time-Periods And Comparing-Data-Across-Date-Ranges
Connect on Linkedin
Try
link : https://www.dropbox.com/s/9jelo8gddv88sq0/Week%20start%20end%20Monday.pbix?dl=0
Week Start date = 'Table'[Date]-1*WEEKDAY('Table'[Date],2)+1
Week End date = 'Table'[Date]+7-1*WEEKDAY('Table'[Date],2)
Week of = FORMAT('Table'[Week Start date],"dd/mm/yyyy") & " "& FORMAT('Table'[Week End date],"dd/mm/yyyy")
Appreciate your Kudos. In case, this is the solution you are looking for, mark it as the Solution. In case it does not help, please provide additional information and mark me with @
Thanks. My Recent Blog -
Winner-Topper-on-Map-How-to-Color-States-on-a-Map-with-Winners , HR-Analytics-Active-Employee-Hire-and-Termination-trend
Power-BI-Working-with-Non-Standard-Time-Periods And Comparing-Data-Across-Date-Ranges
Connect on Linkedin
- Anonymous6 years agoNot applicable
Thanks Amith... it works.