Hi Everyone, I'm trying to create a report for visualizing our prodictin plan for our management for easy review. I'd like to achieve something like this: I couldn't find any mat...
- 8 years ago
Use the Gantt custom visual with Grouped tasks turned on in the General Format. You will need a task duration rather than end date and you'll get exactly the layout you need
Andy_Chandler
8 years agoFrequent Visitor
Use the Gantt custom visual with Grouped tasks turned on in the General Format. You will need a task duration rather than end date and you'll get exactly the layout you need
Andy_Chandler
8 years agoFrequent Visitor
- csabil8 years ago
Advocate II
Dear Andy_Chandler,
thank you very much, the grouping was the key. Exactly what I was looking for.