Forum Discussion
Visualization in Power BI
I am new to Power BI but able to manage around few times. I am struggling to create cumulative of the data that I have. and some on time %. My file contains the following screenshot below. My visualization would be line and clustered column chart graph with the secondary axis as line chart.
I want to create the following:
1) cumulative Planned date for each milestone by month
2) % ontime = Planned vs Actual
Would appreciate any help and my table name is 'Export Worksheet'
| PROJ_ID | PACKAGE | PACKAGE_DESC | MILESTONE_SET | ORD_SEQ | MILESTONE | PLANNED_DATE | FORECASTED_DATE | ACTUAL_DATE | VARIANCE |
| P300000 | P0001 | Pump | MILESTONE 1 | 10 | Package Initiation | 03-Oct-18 | 10-Oct-18 | 7 | |
| P300000 | P0001 | Pump | MILESTONE 1 | 20 | Technical Specification Started | 12-Oct-18 | 19-Oct-18 | 7 | |
| P300000 | P0001 | Pump | MILESTONE 1 | 30 | Coordination Review Started | 23-Oct-18 | 04-Oct-18 | 04-Oct-18 | -19 |
| P300000 | P0001 | Pump | MILESTONE 1 | 40 | Technical Bid Doc and ATP Issued for Approval | 01-Nov-18 | 08-Oct-18 | -24 | |
| P300000 | P0001 | Pump | MILESTONE 1 | 50 | Bidders List Approved | 12-Nov-18 | 17-Oct-18 | -26 | |
| P300000 | P0001 | Pump | MILESTONE 1 | 60 | Advice to Procurement (ATP) Acknowledged | 21-Nov-18 | 07-Nov-18 | -14 | |
| P300000 | P0001 | Pump | MILESTONE 1 | 70 | Bid Request Released | 30-Nov-18 | 30-Nov-18 | 0 | |
| P300000 | P0001 | Pump | MILESTONE 1 | 80 | Bid Closed | 11-Dec-18 | 11-Dec-18 | 0 | |
| P300000 | P0001 | Pump | MILESTONE 1 | 90 | Package Technical Analysis Completed | 20-Dec-18 | 20-Dec-18 | 0 | |
| P300000 | P0001 | Pump | MILESTONE 1 | 100 | Package Recommendation to Award Issued for Approval | 02-Jan-19 | 02-Jan-19 | 0 | |
| P300000 | P0001 | Pump | MILESTONE 1 | 110 | Package Recommendation to Award Approved by Client | 11-Jan-19 | 11-Jan-19 | 0 | |
| P300000 | P0001 | Pump | MILESTONE 1 | 120 | Technical Document IFC / IFF Issued | 22-Jan-19 | 22-Jan-19 | 0 | |
| P300000 | P0001 | Pump | MILESTONE 1 | 130 | Purchase Order / Contract Issued | 31-Jan-19 | 31-Jan-19 | 0 | |
| P300000 | P0001 | Pump | MILESTONE 1 | 2000 | First Vendor Data Received | 20-Feb-19 | 20-Feb-19 | 0 | |
| P300000 | P0001 | Pump | MILESTONE 1 | 2010 | First Delivery or Mobilization Start | 21-May-19 | 21-May-19 | 0 | |
| P300000 | P0001 | Pump | MILESTONE 1 | 2020 | Last Delivery/Work Completed | 20-Jun-19 | 20-Jun-19 | 0 | |
| P300000 | P0002 | Conveyors | MILESTONE 1 | 10 | Package Initiation | 19-Sep-18 | 01-Oct-18 | 01-Oct-18 | 12 |
| P300000 | P0002 | Conveyors | MILESTONE 1 | 20 | Technical Specification Started | 15-Sep-18 | 10-Oct-18 | 25 | |
| P300000 | P0002 | Conveyors | MILESTONE 1 | 30 | Coordination Review Started | 09-Oct-18 | 19-Oct-18 | 10 | |
| P300000 | P0002 | Conveyors | MILESTONE 1 | 40 | Technical Bid Doc and ATP Issued for Approval | 18-Oct-18 | 30-Oct-18 | 12 | |
| P300000 | P0002 | Conveyors | MILESTONE 1 | 50 | Bidders List Approved | 29-Oct-18 | 08-Nov-18 | 10 | |
| P300000 | P0002 | Conveyors | MILESTONE 1 | 60 | Advice to Procurement (ATP) Acknowledged | 07-Nov-18 | 19-Nov-18 | 12 | |
| P300000 | P0002 | Conveyors | MILESTONE 1 | 70 | Bid Request Released | 16-Nov-18 | 28-Nov-18 | 12 | |
| P300000 | P0002 | Conveyors | MILESTONE 1 | 80 | Bid Closed | 27-Nov-18 | 07-Dec-18 | 10 | |
| P300000 | P0002 | Conveyors | MILESTONE 1 | 90 | Package Technical Analysis Completed | 06-Dec-18 | 18-Dec-18 | 12 | |
| P300000 | P0002 | Conveyors | MILESTONE 1 | 100 | Package Recommendation to Award Issued for Approval | 17-Dec-18 | 28-Dec-18 | 11 | |
| P300000 | P0002 | Conveyors | MILESTONE 1 | 110 | Package Recommendation to Award Approved by Client | 27-Dec-18 | 09-Jan-19 | 13 | |
| P300000 | P0002 | Conveyors | MILESTONE 1 | 120 | Technical Document IFC / IFF Issued | 08-Jan-19 | 18-Jan-19 | 10 | |
| P300000 | P0002 | Conveyors | MILESTONE 1 | 130 | Purchase Order / Contract Issued | 17-Jan-19 | 29-Jan-19 | 12 | |
| P300000 | P0002 | Conveyors | MILESTONE 1 | 2000 | First Vendor Data Received | 06-Feb-19 | 18-Feb-19 | 12 | |
| P300000 | P0002 | Conveyors | MILESTONE 1 | 2010 | First Delivery or Mobilization Start | 07-May-19 | 19-May-19 | 12 | |
| P300000 | P0002 | Conveyors | MILESTONE 1 | 2020 | Last Delivery/Work Completed | 06-Jun-19 | 18-Jun-19 | 12 | |
| P300000 | P0004 | New Package | MILESTONE 1 | 10 | Package Initiation | 26-Apr-18 | 26-Apr-18 | 02-May-18 | 6 |
| P300000 | P0004 | New Package | MILESTONE 1 | 20 | Technical Specification Started | 03-May-18 | 03-May-18 | 0 | |
| P300000 | P0004 | New Package | MILESTONE 1 | 30 | Coordination Review Started | 10-May-18 | 10-May-18 | 03-May-18 | -7 |
| P300000 | P0004 | New Package | MILESTONE 1 | 40 | Technical Bid Doc and ATP Issued for Approval | 31-May-18 | 31-May-18 | 0 | |
| P300000 | P0004 | New Package | MILESTONE 1 | 50 | Bidders List Approved | 14-Jun-18 | 14-Jun-18 | 0 | |
| P300000 | P0004 | New Package | MILESTONE 1 | 60 | Advice to Procurement (ATP) Acknowledged | 18-Jun-18 | 18-Jun-18 | 0 |
13 Replies
- v-jiascu-msftMicrosoft Employee
Hi luqmaanr,
Can you share the expected result, please?
1. Which value will be on the Column, which value will be on the line?
2. Which value will be cumulated?
3. Please download the demo in the attachment. Is it the one?
Best Regards,
Dale- luqmaanrFrequent Visitor
Hi Dale
Thanks for responding, much appreciated.
1) Planned, Forecast and Actual will be the column data, cumulative planned, cumulative forecast and cumulative actual will be line as secondary axis
2) Planned, forecast and actual will be cumulated
See attached photo as an example from the below table.
Bidders List Approved - PLAN Bidders List Approved - FORECAST Bidders List Approved - ACTUAL Bidders List Approved **bleep** Planned Bidders List Approved **bleep** Forecast Bidders List Approved - **bleep** Actual Jan-18 1 1 1 0 0 0 Feb-18 2 3 4 2 3 4 Mar-18 11 6 6 13 9 10 Apr-18 15 12 10 28 21 20 May-18 5 5 5 33 26 25 Jun-18 5 8 9 38 34 34 Jul-18 5 4 5 43 38 39 Aug-18 9 8 7 52 46 46 Sep-18 11 13 14 63 59 60 Oct-18 3 7 4 66 66 Nov-18 3 6 0 69 72 Dec-18 0 0 0 69 72 Jan-19 1 1 0 70 73 Feb-19 0 0 0 70 73 Mar-19 5 1 0 75 74 Apr-19 0 1 0 75 75 May-19 0 0 0 75 75 Jun-19 0 0 0 Jul-19 0 0 0 Aug-19 0 0 0 Sep-19 0 0 0 Oct-19 0 0 0 Nov-19 0 0 0 Dec-19 0 0 0 Jan-20 0 0 0 Feb-20 0 0 0 Mar-20 0 0 0 - v-jiascu-msftMicrosoft Employee
Hi luqmaanr,
The problem here is how we can get the data in your second post from the data in your first post. I can't find any connection.
Can you modify the demo I attached before?
Best Regards,
Dale
- luqmaanrFrequent Visitor
The issue still not resolved. I have attached example in my previous posting.