Forum Discussion

luqmaanr's avatar
luqmaanr
Frequent Visitor
7 years ago

Visualization in Power BI

I am new to Power BI but able to manage around few times.  I am struggling to create cumulative of the data that I have. and some on time %.  My file contains the following screenshot below. My visualization would be line and clustered column chart graph with the secondary axis as line chart.

I want to create the following:

1) cumulative Planned date for each milestone by month

2) % ontime = Planned vs Actual

 

Would appreciate any help and my table name is 'Export Worksheet'

 

 

PROJ_IDPACKAGEPACKAGE_DESCMILESTONE_SETORD_SEQMILESTONEPLANNED_DATEFORECASTED_DATEACTUAL_DATEVARIANCE
P300000P0001PumpMILESTONE 110Package Initiation03-Oct-1810-Oct-18 7
P300000P0001PumpMILESTONE 120Technical Specification Started12-Oct-1819-Oct-18 7
P300000P0001PumpMILESTONE 130Coordination Review Started23-Oct-1804-Oct-1804-Oct-18-19
P300000P0001PumpMILESTONE 140Technical Bid Doc and ATP Issued for Approval01-Nov-1808-Oct-18 -24
P300000P0001PumpMILESTONE 150Bidders List Approved12-Nov-1817-Oct-18 -26
P300000P0001PumpMILESTONE 160Advice to Procurement (ATP) Acknowledged21-Nov-1807-Nov-18 -14
P300000P0001PumpMILESTONE 170Bid Request Released30-Nov-1830-Nov-18 0
P300000P0001PumpMILESTONE 180Bid Closed11-Dec-1811-Dec-18 0
P300000P0001PumpMILESTONE 190Package Technical Analysis Completed20-Dec-1820-Dec-18 0
P300000P0001PumpMILESTONE 1100Package Recommendation to Award Issued for Approval02-Jan-1902-Jan-19 0
P300000P0001PumpMILESTONE 1110Package Recommendation to Award Approved by Client11-Jan-1911-Jan-19 0
P300000P0001PumpMILESTONE 1120Technical Document IFC / IFF Issued22-Jan-1922-Jan-19 0
P300000P0001PumpMILESTONE 1130Purchase Order / Contract Issued31-Jan-1931-Jan-19 0
P300000P0001PumpMILESTONE 12000First Vendor Data Received20-Feb-1920-Feb-19 0
P300000P0001PumpMILESTONE 12010First Delivery or Mobilization Start21-May-1921-May-19 0
P300000P0001PumpMILESTONE 12020Last Delivery/Work Completed20-Jun-1920-Jun-19 0
P300000P0002ConveyorsMILESTONE 110Package Initiation19-Sep-1801-Oct-1801-Oct-1812
P300000P0002ConveyorsMILESTONE 120Technical Specification Started15-Sep-1810-Oct-18 25
P300000P0002ConveyorsMILESTONE 130Coordination Review Started09-Oct-1819-Oct-18 10
P300000P0002ConveyorsMILESTONE 140Technical Bid Doc and ATP Issued for Approval18-Oct-1830-Oct-18 12
P300000P0002ConveyorsMILESTONE 150Bidders List Approved29-Oct-1808-Nov-18 10
P300000P0002ConveyorsMILESTONE 160Advice to Procurement (ATP) Acknowledged07-Nov-1819-Nov-18 12
P300000P0002ConveyorsMILESTONE 170Bid Request Released16-Nov-1828-Nov-18 12
P300000P0002ConveyorsMILESTONE 180Bid Closed27-Nov-1807-Dec-18 10
P300000P0002ConveyorsMILESTONE 190Package Technical Analysis Completed06-Dec-1818-Dec-18 12
P300000P0002ConveyorsMILESTONE 1100Package Recommendation to Award Issued for Approval17-Dec-1828-Dec-18 11
P300000P0002ConveyorsMILESTONE 1110Package Recommendation to Award Approved by Client27-Dec-1809-Jan-19 13
P300000P0002ConveyorsMILESTONE 1120Technical Document IFC / IFF Issued08-Jan-1918-Jan-19 10
P300000P0002ConveyorsMILESTONE 1130Purchase Order / Contract Issued17-Jan-1929-Jan-19 12
P300000P0002ConveyorsMILESTONE 12000First Vendor Data Received06-Feb-1918-Feb-19 12
P300000P0002ConveyorsMILESTONE 12010First Delivery or Mobilization Start07-May-1919-May-19 12
P300000P0002ConveyorsMILESTONE 12020Last Delivery/Work Completed06-Jun-1918-Jun-19 12
P300000P0004New PackageMILESTONE 110Package Initiation26-Apr-1826-Apr-1802-May-186
P300000P0004New PackageMILESTONE 120Technical Specification Started03-May-1803-May-18 0
P300000P0004New PackageMILESTONE 130Coordination Review Started10-May-1810-May-1803-May-18-7
P300000P0004New PackageMILESTONE 140Technical Bid Doc and ATP Issued for Approval31-May-1831-May-18 0
P300000P0004New PackageMILESTONE 150Bidders List Approved14-Jun-1814-Jun-18 0
P300000P0004New PackageMILESTONE 160Advice to Procurement (ATP) Acknowledged18-Jun-1818-Jun-18 0

13 Replies

    • luqmaanr's avatar
      luqmaanr
      Frequent Visitor

      Hi Dale

       

      Thanks for responding, much appreciated.

       

      1) Planned, Forecast and Actual will be the column data, cumulative planned, cumulative forecast and cumulative actual will be line as secondary axis

      2) Planned, forecast and actual will be cumulated

       

      See attached photo as an example from the below table.

       

        Bidders List Approved - PLANBidders List Approved - FORECASTBidders List Approved - ACTUALBidders List Approved   **bleep** PlannedBidders List Approved   **bleep** ForecastBidders List Approved - **bleep** Actual
              
      Jan-18 111000
      Feb-18 234234
      Mar-18 116613910
      Apr-18 151210282120
      May-18 555332625
      Jun-18 589383434
      Jul-18 545433839
      Aug-18 987524646
      Sep-18 111314635960
      Oct-18 3746666 
      Nov-18 3606972 
      Dec-18 0006972 
      Jan-19 1107073 
      Feb-19 0007073 
      Mar-19 5107574 
      Apr-19 0107575 
      May-19 0007575 
      Jun-19 000   
      Jul-19 000   
      Aug-19 000   
      Sep-19 000   
      Oct-19 000   
      Nov-19 000   
      Dec-19 000   
      Jan-20 000   
      Feb-20 000   
      Mar-20 000   
      • v-jiascu-msft's avatar
        v-jiascu-msft
        Microsoft Employee

        Hi luqmaanr,

         

        The problem here is how we can get the data in your second post from the data in your first post. I can't find any connection. 

        Can you modify the demo I attached before?

         

        Best Regards,
        Dale

    • luqmaanr's avatar
      luqmaanr
      Frequent Visitor

      The issue still not resolved. I have attached example in my previous posting.