Hi All,
Need to show committed date vs completion date visual representation for all the items that are Completed on time/ completed after delay. Below is the sample data.
| Item # | Status | Committed Date | Completion Date |
| 1 | Completed on Time | 6/10/2022 | 5/5/2022 |
| 2 | Completed after delay | 7/15/2022 | 12/1/2022 |
| 3 | Completed on Time | 1/25/2023 | 12/5/2022 |
| 4 | Completed on Time | 8/2/2022 | 7/7/2022 |
| 5 | Completed after delay | 5/5/2021 | 6/6/2022 |
Not sure which visual to use to represent them. Please help.
Solved! Go to Solution.
Hi @Anonymous ,
You could try to use pie chart for represent them:
Please refer the attached .pbix file.
Best regards,
Community Support Team_Binbin Yu
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.
Hi @Anonymous ,
You could try to use pie chart for represent them:
Please refer the attached .pbix file.
Best regards,
Community Support Team_Binbin Yu
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.
@Anonymous , See if the use of a single date table and userelationship can help