Hi,
I have a requirement to display the shift roaster in power BI. Below is my Excel data which users wants to see on a calendar.
I used Calendar Visual by MAQ software for the representation, but here it is highlighting only Mon to Thursday days rather than highlighting Mon to Friday.
Can someone suggest me what is wrong with the graph or is there any better way of representation of the shift roaster in Power BI.
Thanks In Advance,
Neelofar Shama.
Solved! Go to Solution.
Hi @Anonymous ,
It is same as yours when I test in my side. It seems to be a lot of issues when I look into reviews for the custom visual. Would you please try to use gantt for shift Roster? Here is a good sample for your reference: https://www.mssqltips.com/sqlservertip/5261/schedule-analysis-using-gantt-chart-in-power-bi-desktop/
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.
Best Regards,
Dedmon Dai
Hi @Anonymous ,
It is same as yours when I test in my side. It seems to be a lot of issues when I look into reviews for the custom visual. Would you please try to use gantt for shift Roster? Here is a good sample for your reference: https://www.mssqltips.com/sqlservertip/5261/schedule-analysis-using-gantt-chart-in-power-bi-desktop/
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.
Best Regards,
Dedmon Dai
March 31 - April 2, 2025, in Las Vegas, Nevada. Use code MSCUST for a $150 discount!
User | Count |
---|---|
91 | |
90 | |
83 | |
73 | |
49 |
User | Count |
---|---|
167 | |
149 | |
98 | |
73 | |
57 |