Timeline & Milestones

Hello,

 

I have data at this format. Because of Star-Schema I would not to rearrange/pivot my data. They are based at this format, which is fine:

ProjectStartEndMilestone
P101.03.202401.07.202501.06.2024
P201.06.202301.04.202701.05.2024
P301.08.202601.09.202801.04.2027

 

My plan is to create a gantdiagramm/barchart with the milestones and the project duration for thes projects.

Origin the projectduration and gantdiagramm is working fine, but whith including the milestones the diagramm failes.

 

So is there any tip/ solution to get a gant diagramm without rearranging the data? ( Like at the post:Creating a timeline visual with milestones - Microsoft Fabric Community). I haven't found a suitable soultion yet.

 

Many thanks for any advice.

 

Planned visual (stars = milestones):

 

  • Anonymous's avatar
    Anonymous
    2 years ago

    Hi Do57792 ,

    Based on the description, try to use the PowerGantt Chart custom visual. Add the column to the start and end. Or, you can try using Gantt Chart by MAQ Software.

    Best Regards,

    Wisdom Wu

    If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

1 Reply

  • Anonymous's avatar
    Anonymous
    Not applicable

    Hi Do57792 ,

    Based on the description, try to use the PowerGantt Chart custom visual. Add the column to the start and end. Or, you can try using Gantt Chart by MAQ Software.