Timeline Slicer 2.4.0 Bug

Having issues witrh the Timeline Slicer as had set the fiscal year for June 1st with Sunday being the 1st day of the week though now the week numbers are not correct as of this month.

Example, week 52 is correct as the date range is from Sunday 19th of May to the Saturday 25th of May. Week 53 however is Sunday 26th of May to Friday 31st instead of Saturday 1st of July (I understand the issue here) and then it has week 1 as the single day of Saturday July 1st and week 2 starts on the 2nd of June.

 

To compensate, I have changed the fiscal date to June 2nd though for 2025, this may cause grief as 1st of June will be the Sunday. Not sure if there may be an easy fix to this. Note that this temp fix above also has 2 months under June as it has the 1st of June as 2024 then a 2nd June for 2025. I hope this makes sense.